KPI for design works

Hi Planners,

How to define the KPIs for design works?

Regards,

Muataz

Z
Zoltan Palffy 👤 Member for 16 years 10 months

track your deliverables look at the actual manhours and associated cost to achieve the dleiverables vs the planned budgeted manhours and cost for these deliverables.

you can do it by drawing or drawing package

or 30% submittal, 60% sumbittal, 90% submittal and IFC submittal