Lags and type of duration format

Hi All,

Please can you advise on the following-

My programme activities are showing incosistent time units on my lags and slope. The activities are showing a mixture of seconds, minutes, hours and days on my activities.

Is there a way i can select a consistent format for all activities to have their lags calculated in days, weeks?

Thank you in advance.

 

Regards,

Farhad

M
Mike Testro 👤 Member for 20 years 5 months

Hi Farhad

In the column you can format the duration by the Format Cells dropdown.

You can do the same by selectiong the link and change the suffix ie 15w or 15d.

As a general rule you should only use lead lags for curing or drying out periods and then it should be set as calendar days - 15ed.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts