Resource leveling in PRA

Hello planners,

Where could I find some comprehensive documentation about the nudge and resource leveling process in Primavera Risk Analysis?

Having tried to level the same project in P6, MS Project, Spider and finally PRA, I find that PRA does not reschedule the project the same way as the 3 others.

Thank you

V
Vladimir Liberzon 👤 Member for 25 years 4 months

Alexandre,

Critical Chain method is about creating and managing buffers.

If you want to use buffers that are defined as the result of risk simulation then it is not Critical Chain Project Management method but Success Driven Project Management method: http://www.spiderproject.com/images/img/pdf/Success%20Driven%20Project%…

It can be used with any software that can calculate probabilities of meeting project targets.

But as I wrote earlier PRA and P6 use different leveling algorithms and with limited resources PRA calculations can not be applied to P6 resource constrained schedules.

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Thank you both,

could the PRA resource leveling algorithm include some part of the Critical Chain method?

Alexandre

D
David Kelly 👤 Member for 21 years 7 months

Vladimir is correct, everyone uses a different method, there is no documentation describing how any of the Primavera products do this. It is  as proprietary in the way that the critical path analysis with a forward and backwards path is public domain

The correct methodology is the Minimum Moment Matrix solution as extended to a three dimensional matrix to allow for a priority ranking for resource fit, as written by me in about 1985. But you will need a working Data General mini computer. I couldn't do the maths anymore.

V
Vladimir Liberzon 👤 Member for 25 years 4 months

Alexandre,

every PM software uses its own leveling algorithms. So the results of resource leveling by different tools and the resulting planned sequence of activity execution may differ. Even the same PM software produces different schedules if to use different leveling priorities.

That is why it does not make sense to use any external software including PRA for risk simulation of resource constrained schedules. They create probability distributions for management that uses their own planning rules, not the rules that are used by the initial package.

If you need correct risk management for resource constrained projects use Spider Project for both resource management and risk simulation.

Best Regards,

Vladimir

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts