A change order is a notification that something has changed on the project - it is a Project Controls tool. A variation is a commerical document used to notify the client of a commerical change on the project
A change can be a scope change, a design change, or a trend. Not all change orders lead to variations. A scope change is invariably a variation as it relates to the defined contractual scope being changed. A design change may be seen as "in-scope" or design development and may not trigger a variation. A trend may be a forecast of time delay or saving, or cost over or under run forecast, or events that are technically in scope but have an impact on time or scope (e.g. wet weather, approvals). Trends in isolation may not lead to a variation, hower a series of trends may be enough to prove a contractual delay or issue and result in a varation.
Both are the same. The name would be specified in your Contract as " What you would call it if it is not included in your Actual Scope. Either it would be known as Change Order or Variation Order.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
A change order is a notification that something has changed on the project - it is a Project Controls tool. A variation is a commerical document used to notify the client of a commerical change on the project
A change can be a scope change, a design change, or a trend. Not all change orders lead to variations. A scope change is invariably a variation as it relates to the defined contractual scope being changed. A design change may be seen as "in-scope" or design development and may not trigger a variation. A trend may be a forecast of time delay or saving, or cost over or under run forecast, or events that are technically in scope but have an impact on time or scope (e.g. wet weather, approvals). Trends in isolation may not lead to a variation, hower a series of trends may be enough to prove a contractual delay or issue and result in a varation.
Hi Nazir,
Both are the same. The name would be specified in your Contract as " What you would call it if it is not included in your Actual Scope. Either it would be known as Change Order or Variation Order.
Thanks
Jithin