Project Management Issues Discussion Member for 9 years 4 months Member for 9 years 4 months Submitted by madhukumar.p on Wed, 2016-06-22 09:15 Permalink Helo Everyone ,Can someone Helo Everyone , Can someone help me how to implement "line of Balance" method in a highway project . Member for 20 years 6 months Member for 20 years 6 months Submitted by md ariff md thayoob on Wed, 2010-01-06 07:53 Permalink RE: Templates for Highway Projects Thanks Samer Member for 17 years 3 months Member for 17 years 3 months Submitted by Samer Zawaydeh on Tue, 2010-01-05 13:14 Permalink RE: Templates for Highway Projects Dear MD, Most recommendation here would be to build you own Program of Works. This can be done by reading the specification, drawings, and BOQs. The activities, sequence, resources, and duration, can be determined with the construction crews at site. But in general, you will have the followign divisions: I. Roads a. Excavation and Fill b. Subbase c. Basecourse d. Asphates II. Structures; buildings, bridges, culverts. a. Substructures b. Superstructures III. Electrical IV. Mechanical V. Signage If you have a more detailed question, please let us know. With kind regards, Samer Log in or register to post comments
Member for 9 years 4 months Member for 9 years 4 months Submitted by madhukumar.p on Wed, 2016-06-22 09:15 Permalink Helo Everyone ,Can someone Helo Everyone , Can someone help me how to implement "line of Balance" method in a highway project .
Member for 20 years 6 months Member for 20 years 6 months Submitted by md ariff md thayoob on Wed, 2010-01-06 07:53 Permalink RE: Templates for Highway Projects Thanks Samer
Member for 17 years 3 months Member for 17 years 3 months Submitted by Samer Zawaydeh on Tue, 2010-01-05 13:14 Permalink RE: Templates for Highway Projects Dear MD, Most recommendation here would be to build you own Program of Works. This can be done by reading the specification, drawings, and BOQs. The activities, sequence, resources, and duration, can be determined with the construction crews at site. But in general, you will have the followign divisions: I. Roads a. Excavation and Fill b. Subbase c. Basecourse d. Asphates II. Structures; buildings, bridges, culverts. a. Substructures b. Superstructures III. Electrical IV. Mechanical V. Signage If you have a more detailed question, please let us know. With kind regards, Samer
Member for
9 years 4 monthsHelo Everyone ,Can someone
Helo Everyone ,
Can someone help me how to implement "line of Balance" method in a highway project .
Member for
20 years 6 monthsRE: Templates for Highway Projects
Thanks Samer
Member for
17 years 3 monthsRE: Templates for Highway Projects
Dear MD,
Most recommendation here would be to build you own Program of Works. This can be done by reading the specification, drawings, and BOQs.
The activities, sequence, resources, and duration, can be determined with the construction crews at site.
But in general, you will have the followign divisions:
I. Roads
a. Excavation and Fill
b. Subbase
c. Basecourse
d. Asphates
II. Structures; buildings, bridges, culverts.
a. Substructures
b. Superstructures
III. Electrical
IV. Mechanical
V. Signage
If you have a more detailed question, please let us know.
With kind regards,
Samer