Good morning All,

I am trying to establish a KPI graph based on weekly activity count of the programme to display the progress of the project.

All I can do is resource the project and and create a histogram based on all resources and export the data to excel.

But I am sure there is another way (way easier and less time consuming) to reach weekly activity counts data and export to excel. I appreciate any  feed back may help.

Regards. 

M
Mike Testro 👤 Member for 20 years 5 months

Hi Tolgay

If you want to know the number of tasks being worked on in any given week just progress the works and then filter on work in progress.

Just add the number of tasks to your spreadsheet.

Best regards

Mike T.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts