start, finish and total float float

Greetings to All.

(it might be a stupid question)

In P6 project layout we use start, finish and total float columns. we have original duration too. My question is on what basis total float is calculated. because total float = late start- Early start or late start - early start

and we dont enter any kind of early or late start or finsh shedule, but still total float is provided. how is it possible. 

(Thanks in Advance)

M
Mike Testro 👤 Member for 20 years 5 months

Hi MD

Latest start is where all the float is used up.

Best regards

Mike T.