In P6 project layout we use start, finish and total float columns. we have original duration too. My question is on what basis total float is calculated. because total float = late start- Early start or late start - early start
and we dont enter any kind of early or late start or finsh shedule, but still total float is provided. how is it possible.
(Thanks in Advance)
You enter project start, activity durations and logic, after schedule run early and late dates are calculated during forward and backward calculations then float values are calculated and all can be shown on the same table.
Hi MD
Latest start is where all the float is used up.
Best regards
Mike T.