I understand that having a negative schedule variance with a positive cost variance is a rare case scenario. Could you please cite me a practical situation where this could be possible ?
Thanks.
Hi,
I understand that having a negative schedule variance with a positive cost variance is a rare case scenario. Could you please cite me a practical situation where this could be possible ?
Thanks.
When works were done slower than expected but actual expenses are lower than planned.