Hi, trying to do a college assignment and mid way through programme, when I enter 1d for a duration it jumps to 6000w. Has anybody had a similar issue or know what setting will rectify this.
Thanks
Duration automatically changing from 1d to 6000w
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Hi,
Check if you have resources in the particular activites and been closed on single day span (Act Start-Finish) it accumulates your planned resource distributio and distort the complete timeline. I just am putting my guess as it occers here in my Schedule several times when we close DELETED Provisional sums acitviities with cost loaded into it.
Regards,
Ameya
Hi Stephen - welcome to planning planet
Never heard of that one before - have you created a buffer task by accident - if so change it back to a normal task.
Next check your calendars both on the task and any resources.
Can you change it back to 1d by either:
Change the dates in the spreadsheet?
Drag the task back with the mouse?
You could have a glitch on the software - try deleting the task and putting it on a new row.
If nothing else then contact Asta Support - I presume you have an up to date licence.