Top Down Forecast Entry (Manual)

Afternoon All,

Hoping you can help me out please.

I am trying to work out how to manually enter forecast & budget values per month. I am happy with bottom up forecasting but more often than not the clients cost engineer creates a monthly rolling forecast (in Excel) that then needs plugging into project/primavera/asta each month against some high level (often WBS level) bars.

Happy with doing this in everything but Asta, so any wisdom on how this can be achieved in Asta would be fab.

Thanks in advance. Adam.

L
Leigh Durnall 👤 Member for 16 years 1 month

You can copy/paste a region of cells between Excel and Asta spreadsheets. Filter out Summary or Expanded tasks though as non-editable values will cause a paste to fail.

Leigh @ Asta

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts