Hi there
Still learning this MS software
Is there a formula for calculating the slip/delay to tasks behind schedule?
Ive baselined and created a planned % complete and have manually marked up progress in the % complete column
is there a formula that looks at both and generates a duration?
Thanks Charlie
Suggest using Excel to help communicate and develop the formulas.
It might be you need an additional UDF and formula to calculate Planned Duration depending on the MSP available fields.
Good Luck,
Rafael
Hi thanks for the reply
these links seem to deal with the varience from baseline to resheduled position
What Im actually trying to achieve is the traditional slip column you would get in ASTA
i.e. 10 day activity is due to complete on the report date but is only 80%
so the 3 columns would look like
Planned 100 (Pasted into this column from updating project and then undoing)
Actual 80 (manually typed)
Slip -2 days
All without reshedulling
Any ideas?
Charlie
Long time I have not used MSP, do not even have a license but maybe this can help:
http://www.projectlearning.net/pdf/I1.1.pdf
http://office.microsoft.com/en-001/project-help/start-variance-fields-H…
http://www.textndata.com/forums/baseline-finish-finish-variance-206769…
http://pm.stackexchange.com/questions/7942/how-to-calculate-execution-v…
Be careful with formulas and the difference between varanace calculated considering only workdays versus variance that also include non-work days.
Good Luck
anyone? is it possible?