HI GUYS CAN SOMEBODY HELP ME WITH SPI AND CPI CALCULATIONS.
Actually I wanted to know the linitations of SPI & CPI.
what is the acceptable limit of SPI and CPI.
Thanks,
HI GUYS CAN SOMEBODY HELP ME WITH SPI AND CPI CALCULATIONS.
Actually I wanted to know the linitations of SPI & CPI.
what is the acceptable limit of SPI and CPI.
Thanks,
Thanks guys, Thsnk you very muich for your wonderful support.
Cheers.
Hi, Abdul. Johannes post is completely correct, but to just take it a little further:
I hope this info is helpful. If you want to explore all this further, I'd recommend ordering my new book Managing Projects as Investments: Earned Value to Business Value, due out from CRC Press in September.
Fraternally in project management,
Steve the Bajan
Hi Abdul
SPI is a Schedule Performance Index value is expressed as a ratio. SPI = Earned Value Cost/Planned value cost.
A value of less then then one indicates that less work was actually performed than was scheduled.
CPI is Cost Performance Index is expressed as a ration CPI= Earned Value Cost/ Actual cost.
A value less the one indicates that actual costs have exceeded the value of work performed.
The acceptable are different for every schedule. Suggest to aim for a range of 0.95-1.15 for both cases
Trust this helps
Regards Johannes