I am wondering if anyone can help me please? I am working on a Wind Farm project and putting the schedule through Primavera Risk analysis . What is the best Duration Uncertainty to use – Triangle or Trigen? Thank you Claire
Best Duration Uncertainty to use – Triangle or Trigen
Forum Sponsor
Top Posters
henrigpc
0 posts
Hashil Ali
0 posts
Nigel Hussey
1 posts
James Williams
74 posts
Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
You have my sympathy.
Huh. That there's pretty rude, in't?
Dunning-Kruger is a sad thing, and pretty much incurable.
Cheeri-O.
Steve the Bajan
Dennis wrote: "...I would use the trigen if (big if) I thought the ranges given were understating the risk - my respondents were risk accepting, giving optimistic estimates. I would use triangle if I thought they fully understood/appreicated the risk(s)."
That's sort of the big problem with Monte Carlo risk simulation packages, isn't it? Nobody knows what the objectively "correct" number is, so if we run it on one default and don't like the answer, we tweak it until we get the answer we wanted all along. In other words, we decide what number we want and then use pseudo-science to justify our gut instincts. it's the classic example of "garbage in, gospel out".
Monte Carlo systems can provide valuable information if:
But almost no one does any of that -- it’s too much work. Instead, they pluck three estimates out of thin air and then they run the simulation using a default, And if they don't like the results fromthat default, they use another one. And, as Dennis suggests, the whole purpose is to satisfy a customer who knows nothing about the process but is impressed when told: "It must be accurate -- it came out of a computah!"
Fraternally in project management,
Steve the Bajan
The best PDF to represent activities durations is Lognormal distribution
Please refer to the following paper
Claire:
For me, the difference is whether or not my respondents are risk adverse, risk accepting, or neutral. Of the two possible distrubutions you cite, I would use the trigen if (big if) I thought the ranges given were understating the risk - my respondents were risk accepting, giving optimistic estimates. I would use triangle if I thought they fully understood/appreicated the risk(s). Since it is relatively easy to change the risk distributions in the layout, I might run both just for grins. I would run BetaPert to model the risk adverse case.
Hope this helps.
http://www.mediafire.com/view/s8nm7i7ju64kv9v/Risk_-_PDF_-_The_best_fit…
http://www.mediafire.com/view/xg9mn7f9u20j0m5/Risk_-_PDF_-_Most_appropr…