This is a good article. I will be sure to share with others. It is very similar to this article: "9 Tips for Dealing with an Over Allocated Resource"
More smoke and mirrors. The simple fact is, if you don’t have enough resources and management is doing its job to the best of its ability the work takes longer.
The linked blogs first option is ‘fast track where you can’. Fast tracking overlaps phases that would normally be done sequentially.
Overlapping phases that would normally be done at different time means you need double the resources – you need enough resources to work on both phases at the same time but the problem is you don’t have enough resources to work on the current phase. Therefore you have twice as much work not being done!
The only useful advice is the last point – ‘don’t pretend it is OK’
For more on accelerating project work see: http://www.mosaicprojects.com.au/WhitePapers/WP1059_Schedule_Compression.pdf