Hello Tilos users,
I would appreciate if somebody explains the difference between Actula resources and Planned resources in Tilos.
Are Actual resources mandatory if I want to update the project progress by using resources actual work? Or are they something really different?
The online help is very clear in describing the way to add actual resources by hand or by using the Collect actuals option, but it does not say a word about why to use these Actual resources.
Thank you for your help,
Alexandre
Hello Shalabh,
Creating the histogram in Excel to be able to compare Initial Effort and Actual Effort is what I suspected. I will try to use a user defined field in Tilos, and I will let you know
By the way, do you have anything about the way color codes are working in the resource barchart?
All the best,
Alexandre
meanwhile let me ask the same in differnt forum. ....
Hi Alexandre,
I believe that you have to do that analysis in Excel to distinguish the Planned Vs Remaining Effort.
I have tried to do that in TILOS but in vain.
Anyways, you can export the resource units from TILOS to Excel.
Regards,
Shalabh
Thank you, Shalabh
I have done a few tests and trials with Planned and Actual Resources, and I understand now how it works, with the help of your explanations
I am now trying to setup a resource histogram with Planned Effort and Actual Effort; I need to show the initial planned effort all along the project, but I have noticed that the Planned Effort bars only show the remaining planned effort.
Do you have a trick to show the initial planned effort instead of the remaining planned effort?
Best rergards