I have been given a programme to review. It Asta V12. When I re-schedule, I find 2 tasks that have
- No Links (in or out)
- No constraints of any kind
After I re-schedule (F9), the tasks “just sit there”. They do not move back to the re-schedule date. I can “move” them to another date, and again they just sit there. What is causing this??
Ronan
Thanks
Hi Ronan
Goto Tools > Options > Reschedule and you will see three options for tasks with no links.
Yours is pobably set to > "Leave as drawn within constraints"
Choose any of the other two to get a different option - the task will probaly fall back to day 1.
Best option is to put some logic onto it.
Best regards
Mike Testro