Hi, I'm using Primavera P6, and I've attended beginners course and read most of Harris' Project planning and control using Primavera P6...
I find the book very usefull, but I miss the best practice discussions. Anyone read anything good or know of good resources on best practice for planning/scheduling/follow up/?
Haakon
Hi Hakon,
I am certainly no expert in the field, however I have been recently impressed with the following publication.
It is freely available electronically on the web.
Planning & Scheduling Excellence Guide (PASEG)
Published Release v2.0
6/22/2012
National Defense Industrial Association (NDIA)
Procurement Division - Program Management Systems Committee (PMSC)
Regards,
Ramon
Hi Hakon
The Chartered Institute of Building has published "Best Practice in the Control of Time in Complex Projects".
That should be a good starting point.
Best regards
Mike Testro