Actual and base version. Add new info?

 

Sorry for bad language. As update baseline project with  new information?  Baseline project was placed with docs old, in process of construction, amount may be changed, new information is recieved . Plus new construction documents is going out. Change and track each activity and update data in baseline is very hard to me. Maybe  you have solutions?

V
Vladimir Liberzon 👤 Member for 25 years 4 months

Alexey,

if you want to be able to compare current schedule withh the baseline both shall be updated. In other case you will not be able to apply Erned Value Analysis and track activity performance against the baseline.

But you can apply other methods of project performance analysis. I may suggest to assign target dates and target costs to the project phases and just analyze if your targets were achieved. In this case the baseline is just a set of target dates and costs and in this case it is not necessary to update it when more detailed information becomes available. You still will be able to compare planned and actual dates and costs with the approved targets, analyze trends and risks, manage project buffers.

Best Regards,

Vladimir

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts