Qualitative Risk Assigning

Can we assign qualitative risk to set of activities from a particular WBS by just selcting WBS in Primavera Risk Analysis? To assign risk by checking individual activity is very time consuming.

Thanks

 Umerfarook Deshmukh

D
Dennis Hanks 👤 Member for 19 years 1 month

Umerfarook/Jenn;

Quick Risk Template in PRA will let you assign ranges via activity codes and Risk Factors will let you assign the Risk to any 'sortable' group by using Fill down and the Risk Factors Sheet.  It could be easier, but it is not impossible.

J
Jenn Weber 👤 Member for 15 years 4 months

Hi Umerfarook, 

Unfortunately in Primavera Risk Analysis you do have to assign each activity individually.  I agree it is very time consuming! Acumen has just launched a new risk analysis software for both schedule and cost risk that allows you to assign risk values for groups of activities.  You can do this by WBS or group the activities by a common attribute (Contractor, Location, Activity Type, etc.).

I'd be happy to set up a demonstration for you to show you this feature (as well as the many other time and effort savings of Acumen Risk over Primavera Risk Analysis) or you can visit our website for more information. 

http://www.projectacumen.com/products/acumen-risk

Thanks, 

Jenn Goodrich

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts