additional work

Hi All,

I was told by the client to proceed to carry out the additional work by verbal instruction and i have check with my PM to me to proceed and the commercial will talk later. I feel something wrong? is it the right thing to proceed without agreeing the cost???

Regard

Ron

R
Raymund de Laza 👤 Member for 16 years 6 months

Ron,

You can send an RFI (Request for Information) to clarify the subject.

Inform them them that the verbal instruction will cost the contractor blah blah blah ...... to proceed with.

In this case, they will reply and that the subject is now officially in Black & White.

 

R
ronron martinez 👤 Member for 16 years 6 months

Hi Ali

 

Most of my previous project work been carry out without agreeing the cost, after the work completed and quotation submitted the client bargain till no room to move and unfair to contractor?

Regard

Ron

G
Gary Whitehead 👤 Member for 17 years 2 months

Most standard contracts allow for the client to instruct additional work to proceed before the contractor has submitted the quotatiion. Even before the full scope of the works is agreed.

However these should be something in writing to protect the contractor. -This could be formal instruction, signed minutes, or even an email is better than nothing.

Some jobs aren't run contractually though. -If your PM feels his relationship with the client is such that he is prepared to proceed on trust, then that's his decision.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts