Hello All,
Does anyone have experience or knowledge on how Asta Powerproject lends iteself to Lean Construction and Last Planner System? Is anyone using the line of balance feature?
Justin
Hello All,
Does anyone have experience or knowledge on how Asta Powerproject lends iteself to Lean Construction and Last Planner System? Is anyone using the line of balance feature?
Justin
Thanks Mike and thank you for the reply.
As far as my first questio, I was looking to see if anyone is using features, such as Line of Balance, to do things like track and view planned versus actual productivity rates, and then use those projections to take necessary actions. I would think these type of features would lend themselves very well to the Last Planner System and Lean.
Hi Justin
Welcome to Planning Planet.
I do not undersatnd your first question.
Lean Planning describes a brainstorming session - usually involving post-it notes and red string.
The results can then be transferred to any software.
The Line of Balance - Time Chain add on to v 12 is most welcome - but you have to set things up in task per line mode first.
I last used it on a 500km oil pipe line up the west coast of India and it was very effective.
Best regards
Mike Testro