Dear Members
I need urgent advice on conversion procedures for conversion of my programme in MSP 2007 to Primavera P7.
I have tried many ways but failed to do successfull conversion.
Please advice what is the correct procedures to convert MSP 2007 to P7
Vineet
Simple way is to save MSP file as XML . You will find this Option when you Click File->Save As .XML.
You can also do import setting in Primavera to get MSP data like Text 1 , Text 2 and other.
Untile Next Time
David Young
http://myprimavera.co.uk
[email protected]
1. Import as an MPX/MPP.
2. Note and delete all headers that have been converted to activity descriptions - you notice them by the fact that theactivity typr becomes 'WBS Summary'
3. Change all other activities type from 'Resource Dependent' to 'Task Dependent' if you so wish
4. Check the calenders, links, constraints.
5. Schedule
NB: Ensure the activie MS Project is closed before you import.
Give me a shout if you get stuck - +447985252112
Regards