Current Baseline - Between set periods

C
Craig Adams 👤 Member for 19 years 7 months

Hello Fellow Asta Travellers,

Would like to create two columns that show specifiic baseline periods from the same baseline - for instance baseline finish dates for year ending 2011 then another column showing 2011 to year ending 2012 out of the same baseline.

Yes could create two baselines however trying to use only one for original baseline (budgeted works) and one for "what if scenarios".

Can anyone help with formula for this?

Look forward to your reply/ies.

Kind regards,

Craig adams

A
Andrew Willard 👤 Member for 16 years 5 months

Hi Craig,

 

If I understand you correctly these two forumals do the trick;

 

For 2011

 

Switch(Task[~CB].Finish >= '1/1/2011' and Task[~CB].Finish <= '31/12/2011', Task[~CB].Finish)

 

and for 2012

 

Switch(Task[~CB].Finish >= '1/1/2012' and Task[~CB].Finish <= '31/12/2012', Task[~CB].Finish)

 

Cheers

 

Andrew

 

M
Mike Testro 👤 Member for 20 years 5 months

Hi Craig

If you have the two baselines open in the view then in table definition you can set up two "Finish" columns - give them a name to suit your baselines.

In the right hand dialogue box under "Data" you can select which of the baselines to display.

Unfortunately the time slice option is greyed out.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts