planned & actual S-curve VS EV

M
moh ham 👤 Member for 15 years 3 months

Kindly advice if the client have the right to request from the contractor to show his resources in the submitted schedule , in case if he hasn't the right how the client or the consultant can evaluate the actual s curve and the EV.

Thank you

R
R. Catalan 👤 Member for 20 years 9 months

Hi Moh,

Submission of allocated resources is already part of the Constractor's daily report. If is tiresome for the Contractor to reflect the actual resources in the schedule, he can request to do it in spreadsheets format (MS Excel) as it would be easy for him to link to other reports (daily report, resource histograms, etc.).

On typical contract scheduling requirements, the Client has the right to request the Contractor to show his resources in the submitted schedule..

Best regards,

R. Catalan

 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts