Cost Assign

Hello everyone 

                           I am cost loading my programme,we use sub contractors for majority of our packages.there is  a lumpsum amount for the subcontract packages. do i assign it propotionally to all the activities ?or is there another way to costing .

can anyone give me guidance as i have never cost loaded my programmes before.where can i get more information on cost loading programmes.

 

Regards S

achin Martin

T
Tekin Guvercin 👤 Member for 19 years

[[wysiwyg_imageupload:354:]]Its really depends how you detailed your schedule. With ASTA you can assign cost to each activity or Sumarry activity. It will distribute with weithed factor. The biggest advantages of ASTA you can assign cost to activities without creating Resource. If you have your subcontractor you can create cost under library and model it in three types. (TIME BASE COST, FIX COST or UNIT COST).

Go to library   create to costs and assign it.

 

I attached here picture with both example. Design A is cost assing to Summary Level (like WBS), Second is detail to activity. Both way possible. if you not solve your problem, contact with me I will send you some detail documents.

 

 

   

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts