Extension of Time Documents

Dear Friends

I am Working on a Palace Project , our project end date was 31 mar 2011 , we submit several impacted schedule whenever we recieve changes and new design , as per our impacted schedule the end date was in novemeber 2011 for the only the released scope , howver there are four to five small building that are part of provisional sums and they have not been released. 

The Client grant us extension of time upto june 2011 for released scope only , however  this extension is not enough as there are stiill many areas where design is pending and also the completion of work requires an other subcontractor from the client which has not yet mobilized on the site

i have to prepare extension of time documents for my Claim , if any of you have any good format , please email me at Use private message service

Thanks

Umer Mehmood

Planning Engineer

M
Mike Testro 👤 Member for 20 years 5 months

Hi Umer

A simple method of claim preparation is to consider each event in turn on a strict chronological order of impact date.

Impact the event on the programme and record the result.

Write a short story describing the event and the effect it had on progress.

Indicate the relevant Contract Clause that applies to the event.

Save the Delay prohramme and move on to the next event.

Continue until all events are impacted

Write a short summary of all the causes and effects and place this as an opening paragraph.

Write a closing summary and place it at the end.

This format is based on the solid 3 stage principle of: Tell what you are going to say - Say it - Tell him what you said.

I hope this helps

Best regards

Mike Testro

U
Umer Mehmood 👤 Member for 17 years 11 months

Dear Roland

Thankyou for replying

i have not prepared any claims before, i just prepared impacted schedule to show the impact on the program

The Consultant is continously asking to prepare a package for the EOT, I dont have any patricular format so that i can satisfy him. Thats the reason if am searching for a format of report so that a professional reply can be made 

 

Thankyou 

 

 

R
Roland Tannous 👤 Member for 16 years 7 months

Are we talking about a Global Claim in here. Solely Delay Claim , Disruption Claim?

Have you prepared any such claims before?

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts