Correcting actual dates

Good day,

After entering actuals for an activity, a finish date is wrong: the activity is not finished but it got an actual finish date assigned. I tried to correct this by going to the performance archive and deleting the finish date, but the field can not be left blank.

How can I correct the activity's status to "Not finished"?

Thanks, best regards.

Carlos.

R
Rafael Davila 👤 Member for 22 years 3 months

 

Go to Performance Archive, select the activity and if you have access rights to access the screen you will be able to make the necessary adjustments to prior periods performance. You shall be able to assign multiple performance interruptions each of different duration and different resource and cost actuals.

To add the Activity to monitoring sheet you can right click the activity and select monitoring.

If prior periods performance is ok and you just need to reactivate the activity select the activity, and enter a remaining duration value.

Regards,

Rafael

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts