You can get the first three sections and the last section from the BOQs and the Issued for Construction Drawings. On the other hand, the Construction depends on the construction team.
For a Road Construction project, I assume that you need to site with your construction team and divide the project into zones and work on them according to priority. Once you have done that the activities generally are:
1. Site Survey.
2. Cut and fill
3. Civil Works according to the cross section of the road that you have; layer 1, 2, 3, etc. You will need to notive the MEP work included inside the civil works and sequence it accordingly.
4. Isolate the concrete structures (box culverts, bridges, etc) and have them in a separte category.
5. You might have side walks, paint, signals, etc after the end of construction. You will have to reveiw the BOQ and Plan them accordingly.
I hope that the information helps a little. If you be more specific and describe the project more, we can assist more.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Dear All,
the main activities for the raods ad infrastructure are cotaining but ot limited to the followig
prjoject commencemet date
Mobilisation
settig out and survey works
obtaiig costructio NOCs from all concerned authortities
trial trenches and varification of the existing services(utiliyies) location
protectio or relocation of existig utilities - as required
layig of ew utilities
submit shop drawings for road works
approval of shop drwings
submit the subcotractors for approval
approval of subcontractors
sumit materials submittals for approval
approva materials submittals
procurement of the matirals
earth works (cut and fill)
prepare the formatio layer
layig of subbase layer
layig of road base layer
spray betuminous prim coat
laying of ashpalt base course
spary tack coat
layig of asphalt weraring course
roads marking
errectig traffic sigs
general site cleaning and prepare the project for handingover
hand over the project.
Hi Raheel
Primavera is noit the best software for linear projects - you should be considering Tilos or Vicos.
Best regards
Mike Testro
Dear Rahel,
The major activities in most projects are
Shop Drawings and Approval
Material Submittals and Approval
Procurement
Construction
Testing and Commissioning and Handing Over.
You can get the first three sections and the last section from the BOQs and the Issued for Construction Drawings. On the other hand, the Construction depends on the construction team.
For a Road Construction project, I assume that you need to site with your construction team and divide the project into zones and work on them according to priority. Once you have done that the activities generally are:
1. Site Survey.
2. Cut and fill
3. Civil Works according to the cross section of the road that you have; layer 1, 2, 3, etc. You will need to notive the MEP work included inside the civil works and sequence it accordingly.
4. Isolate the concrete structures (box culverts, bridges, etc) and have them in a separte category.
5. You might have side walks, paint, signals, etc after the end of construction. You will have to reveiw the BOQ and Plan them accordingly.
I hope that the information helps a little. If you be more specific and describe the project more, we can assist more.
With kind regards,
Samer