Linking PP dates in an excel doc

C
Christine P 👤 Member for 17 years 1 month

Hi all

Im creating a Master Iinformation Release Schedule in excel.  The dates are subject to change so rather than having to change them every time in the excel document, is there any way of linking the dates in the excel document to the dates in the Powerproject file, so that each time the PP dates are changed the MIRS is updated automatically please?

A
Andrew Willard 👤 Member for 16 years 5 months

Hi Christine,

 

I would normally do this by using tabular reports. A report is created in the same format as the report you want. One click is then all that is need to update the report each time. If you want more information or help on this please let me know.

 

Regards

 

Andrew

M
Mike Testro 👤 Member for 20 years 5 months

Hi Christine

I do not know of any link available between cells in the Powerproject spreadsheet and Excell.

You can however copy / paste from any Power Project column into Excell columns.

The problem is that the time values come with it so you have convert it to date numbers.

If you want your date in say Column C then paste the dates into column E

In Column D type =left(d#,10) and that will lift out the pure date data

In column C type =value(d#) and then format it to the date type you want.

Whenever you copy paste date columns back into excell Col E the dates will format correctly.

Make absolutely sure that your powerproject data lines up exactly with you spreadseet columns or your dates will be all over the place.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts