Physical % Complete

Member for

15 years 9 months

Thanks Bo!



I can always trust your skills when it comes to theese kind of qustions.



Regards



Dan

Member for

19 years 8 months

Hi Dan,



Your formula does work, but needs minor adjustment.



If using a Number-field your formula should look like:[Physical % Complete]*[Baseline Work]/60/100 (the parentheses as you have written are optional - in this case)



and if using a Duration-field the formula should be:

[Physical % Complete]*[Baseline Work]/100, but then at the same time remember that under Tools-Options-Schedule Tab, the "Duration is entered in:" should be set to "Hours" to get the right result. However, then you should be aware that what you enter in the "Duration"-column is by default hours unless adding you add the right unit (e.g. d, w, etc.).



If using the Number-field and you want the "hrs" to be written at the back you can just make a new Text-field with the formula: [Numberx] & " hrs"



Regards,



Bo