Carlos Arana 👤 Member for 17 years

Thanks vladimir,
I necked my activities succcessfully.

Maybe the option to display text in different positions relative to a bar in the gant chart could be included in the "Let's challenge spider" topic, P3 can do it.

Best regards,
Carlos.

V
Vladimir Liberzon 👤 Member for 25 years 4 months

Hi Carlos,

if you want to neck Gantt Chart to show work time of any activity and assignment tick "Detailed Information" in the Levelling Options Dialog.

To select what to display in Gantt Chart select "Data on diagram" in Gantt Chart options and then the required field to be displayed. But you can show only one field at the right.

Unfortunately the pictures were not shown and I removed the reference.

Best Regards,

Vladimir

C
Carlos Arana 👤 Member for 17 years

Question 1:

Is there a way to "neck" the gantt bars to show non-work periods defined by calendars?

Question 2:

How do I choose the text to be displayed beside the gantt bars?

By default, it shows the activity name but I would like to display Volume [Remaining] on the right and Volume [Actual] on the left.

R
Rafael Davila 👤 Member for 22 years 3 months

Carlos,



Recommend you save your Diagrams and Tabular Reports as Template files so you can re-use them, same for your Layouts called configurations in Spider Project. Also learn how to transfer Layouts/Configurations and Reports among job files. It is unnecessary to recreate these once you created them one time.



Best Regards,

Rafael

V
Vladimir Liberzon 👤 Member for 25 years 4 months

To show the diagram for any Gantt Chart line (for project, activity, project phase) right click on the line number or on the bar in the Gantt Chart.

In the poop-up menu select General Reports and Diagrams, the what do you want to show. For example select Resources, then choose what resorce to show, select what to show - work hours or quantities, then select an arrow that will move the selected resource from the left to the right window.

Select period (diagram may be shown per hour, day, week, month, etc), unselect cumulative.

On the next screen select the colors, if to show values and that’s all.

To delete any diagram from the screen right click on it and select Delete Diagram.

In Spider Project right clicking on any object you will get pop-up menu thatt shows what can be done with this object.

By the way resource workload is calculated if to press Resource Peak Workload icon in the menu bar.



Best Regards,

Vladimir

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts