Mike Testro 👤 Member for 20 years 5 months

Hi Chris - welcome to PP.



This sort of completion scramble is nothing new and it is not a planning problem but a management one.



There has to be a controlled flow of work and one method is to use a "permit to work" system where in each room a completing trades work is inspected before the next trade is allowed in.



If you have a fully detailed bottom up programme then the planner can assist the work flow records by a daily update on progress of each trade in each room.



If there are multi task - multi location bars then the planner is no use at all.



Best regards



Mike Testro



ps - its not a good idea to leave your phone number or email address in a thread.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts