Let’s Challenge SPIDER
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Vladimir,
"Preventive Maintenance" - Im also not sure if there is a standard definition, I just happen to step on it and made me believe that this type of works exist. How to define it?
Maybe others have any ideas?
Usually there is a year program for the maintenance.
The order of works can be defined by program planner.
Please specify what do you mean by preventive and predictive, I am not sure that understood you correctly.
But I am leaving Russia until Tuesday and will be able to answer only on return.
Best Regards,
Vladimir
Hi Vladimir,
If I may ask, how do you define the sequence of works like preventive or predictive maintenance (not a routine maintenance)?
cheers
Rafael,
I expect that the sequence of maintenance jobs is defined. If not then it is necessary to solve this task first.
Mike will inform us.
Best Regards,
Vladimir
Mike and Vladimir
Are you considering optimizing the movement from job to job by minimizing distance? Let say crew is at grid location no C20 so it first will look for jobs at location C20, if not available then at locations B19, B20, B21, C19, C21, D19, D20, D21?
Going from grid location C20 to grid location W12 when a job at C20 is ready to start is not optimal.
Best regards,
Rafael
Hi Mike,
I am very interested.
I like large programs with resource restrictions.
Are there other restricitions except one drum resource?
Do you plan to create resource management plan finding what optimal amounts of other resources are needed to keep drum resource busy?
I will have more questions if you will keep us informed.
Best Regards,
Vladimir
P.S. Do you use the levelling software other than PowerProject? Why? What software do you use?
Hi Rafael - Hi Vladimir
I have just got a real planning job putting together a roll out programme for all the road maintanance operations for Suffolk County Council for the next three years.
It will probably reach about 130,000 activities on 600 projects per year.
I am using PowerProject enterprise and I am also using the resource levelling software.
They only have 2 road paving machines that need to be kept occupied throughout the paving season so I let powerproject do it for me.
If you are interested I will keep you informed on progress.
Best regards
Mike Testro
Vladimir,
The interface as of now I love it, is uncluttered and the toolbars icons get you directly to over 90% of your navigation, the 10% I prefer it to be at the menu bar. If you add all menu items to the vertical and horizontal toolbars then the toolbars will be cluttered and will slow down your 90% navigation needs, will kill its purpose.
The idea of drop down icons is for in case you need to add some icons to the toolbars this is a possibility to consider, please keep it close to what it is now, don’t over do it.
About an interface to switch on and off functionalities I would only switch off risks and trends. We have pending a discussion about this but now I am getting somewhat busy for another couple of weeks and this topic deserves serious and long debate. Although I am somewhat reluctant to complicate things further with these functionalities I want to listen to what you have to say, I don’t want to repeat the mistake of not listening at you as I did for many years until now.
Best regards,
Rafael
Rafael,
an idea looks attractive but icons take more space than just text and our drop-down menues are too large.
You were right that developing interface it is necessary to use the space wisely.
What we need to do - to create an interface where functionalities can be switched on and off.
Best Regards,
Vladimir
Vladimir,

Did Spider Project ever considered using drop down icons in the toolbars such as the following example used by Autocad? I don’t mean the ribbon as this takes much valuable space, the hundreds if not thousands of menu items in Autocad even requires a combination of the ribbon and drop down icons.
Best regards,
Rafael
Anoon,
Of course you can, but the constant might not be the same as might be based on a different 0 day. This one I figured it out by looking at some values and then by trial and error, for Excel there should be many references or you can figure it out yourself by tial and error until it converges.
What is novel in Spider Project is the concept of using recursive formulas, formulas whose value depends on itself. Of course in Spider Project these are a single loop run.
Best regards,
Rafael
Hi Rafael,
I just thought that I can do the same in excel, using your formula.
cheers
Quote from Vladimir:

_"In Spider Project you can enter recursive formulaes like making all durations two times longer. That is why we do not use automatic (Formulae) calculations."
_"You can set that formulaes that link cost components and cost centers will be executed automatically with any cost calculations. You can set that some formulaes will be executed automatically when you entered actual information and others not."
I still would like to have the additional option to select for “Automatic perform after schedule update”. This option when in conflict with recursive formulas or with other selected formulas to be dimmed and not available for selection until the user resolves the conflict, the same when creating recursive formulas.
In the following example my formula to display Start and Finish dates in nominal days is not computed automatically, I had to create a script to run the two formulae, one for Start and another for Finish.
If I can automate it when not in conflict, I would like to do so. But never eliminate the option for recursive formulas.
Best regards,
Rafael
"histogram window vertical scrolling" that is great news, as you know the horizontal scrolling other software do without showing the schedule above is no good. This will be better than those who can only show a single histogram.
About the script, forget it, so easy with a formula as per your suggestion, you can toggle back and forth at a snap.
I defined two formulae as follows:
Alap=’Alap’
Alap=’Asap’
just execute for desired value to toggle back and forth, yes as you said, a piece of cake, a third formula can easily be done if your model combines ALAP with ASAP so you can go back to the original.
Hi Rafael,
thank you for proposal, we will create histogram window vertical scrolling.
As for Alap schedule try the script but even without scripts it can be esily done if to create formulae Alap=Alap
Applying this formulae and recalculating project schedule you will get AlAP schedule.
Regards,
Vladimir
Vladimir,
Early and Late curves done easily in two separate files, the same for the jobs comparison, because this I do only when baselining there is no issue. The export to Excel function with the baselines and updates shall be no problem.
Eventually might try a script to create the ALAP schedule with a single click of the mouse, but first things first, still crawling, after my first complete job I will be running.
Best regards,
Rafael
Vladimir,
For your knowledge, I use the ALAP data only to show the Owners and others not knowlegeable of CPM that the Progress Curve is not an absolute measure of your job status, not to mention ASAP only. The request is a matter of convenience, not of high priority. I will try with your suggestion.
Regarding the histograms the way Spider Project presents them, aligned with the schedule on top is just what I need. I keep my histograms one per resource as this is easier to understand but it will make it easier to have the lower screen to scroll verically as to accept as many histograms I need to be readily available and latter-on to be printed with my schedules. This request for me is of high priority.
By the way I am starting to explore the cost functions, something I rarely use but for the moment the interface seems very good, still to explore it at the updating time.
Best regards,
Rafael
Hi Rafael,
the histograms part of the window has not scrolling.
We do not expect that people want to have hidden histograms.
This feature can be added if necessary.
You can show Early and Late Cost Curves but not together with the current cost curve.
If you will calculate and save late schedule and budget, then ASAP schedule and budget and compare these two versions you will be able to show both in the same screen. But still only two curves.
Best Regards,
Vladimir
1) I cannot vertical scroll the lower half window, is it a demo limitation?
2) The Labor Cost Curve uses as a reference an ASAP schedule, I can set another Baseline to show ALAP but not in the same screen two baselines, maybe I am wrong, please comment as I am trying to show Early and Late curves on the same screen.
Note costs are not linear as I am exploring other cost functions, using fixed costs on a few activities, don’t pay attention to the model details.
Best regards,
Rafael
Anoon,
You are correct +/- 0.000000%
Maybe because of inefficient software that cannot do good resource leveling and do not show resource critical path some schedulers avoid it at all while others make use of "soft relationships". Soft relationships is what my clients use, I resource load the schedules on my own to double check but although the results are viable they are inefficient.
The true practical value of resource leveling is starting to show up with Spider Project and I would like all software to be as good, this software is raising the bar without you having to learn new science, it does the math for you.
Project Management is like playing music for dancers, if the music is slow the dancers will move slowly, if fast the dancers will go fast, if slow, fast, slow, fast ... dancers will fall. A good Project Manager makes sure the tempo of his job start fast and keeps it this way. This is impossible to do with inefficient resource allocation, with many ups and downs, with available resources being used inefficiently or unused, your labor perception on urgency goes down.
Best regards,
Rafael
Hi Carlos,
thank you for your question. Organization of the group work deserves special discussion.
Spider Project Professional, Desktop Plus and Lite support group work but differently.
Spider Project Professional includes not only project but also portfolio management tools. I understood that your question is about project management.
If the project has subprojects that are managed by different persons and organizations (we call such projects programs or multiprojects) then you will need Spider Project Professional for program management.
You shall also to implement some strict regulations on the time of program data updating. Program scheduling and reporting require the existence of the common data date for all subprojects that belong to the Program. So all program participanta shall enter actual information on the same date and time. These requirements are the same for evrybody who is responsible for updating program data.
Lets suppose that the Program is updated on Tuesdays basing on the program status on Monday evening. So all Program participants shall enter actual status information strictly on the required time (Monday evening) to make the status date the same for all program subprojects. And this shall be done on Tuesday morning before the Program will be rescheduled and reports will be produced.
But subproject managers may require different frequency of data updating. In small subproject it may be necessary to reschedule daily to supply resources for the plans for the day (shift). So subproject managers may need to manage their subprojects separately, with their own data dates, resources, regulations though all of them shall follow program requirements and supply the program planner with the Monday evening statuses of their subprojects on Tuesday morning.
That is why Spider Project uses special organization of the group work with the program data.
Program Planner creates Responsibility Breakdown Structure where phases are the names of responsible managers, activities in these phases are those that belong to their subprojects. Program Planner creates a list of responsible managers and enters the folder paths where to send them their subprojects and where to take updated models. These responsible managers are assigned to the phases in the responsibility structure.
When the command Distribute suprojects is selected by Program Planner Spider Project replicates the Program model and sends to each of responsible managers the models of their subprojects for the autonomous work until the next update. Now subproject managers may work with their own regulations until the next Tuesday (for an example updating the model every day). All of them know that it is necessary to update their models to the status of Monday evening on Tuesday morning because at 10:00 on Tueasday Program Planner will select the command Consolidate subprojects and all information in the program model will updated by the information that exists in the subproject models. This way the new version of the program model will be created and the previous one will be kept in the program archive. The program shall be rescheduled and analyzed, corrective actions may be planned, and after new plan for a week will be accepted Program Planner selects the command Distribute subprojects ...
At the lower levels program planners may use not professional but Desktop version of Spider Project that is much cheaper. They do not need to work in the network, they just need to place their models with Monday evening status to specified folder, to FTP server, or just send by E-mail. The size of Spider Project files is relatively small.
But if you manage relatively small project where project participants just enter actuals (not work with the models adding activities, assigning resources, costs, etc.) then you dont need to replicate project model and use different model of the collaboration. And for this model you can use Spider Project Desktop Plus (two times cheaper than professional version).
You still need Responsibility Structure but this time people are responsible for entering actuals for different activities. Usually they are assigned as resources but sometimes you can decide that actual data shall be entered by somebody else (foremen, etc.).
But this time Spider Project will send not the models of subprojects but table Reporting Forms that include the data of what is planned for current time period (list of planned activities, assigned resources, planned dates, volumes of work, durations, costs, material consumption for all planned activities).
For each parameter this form includes initial, planned and remaining quantities. If actuals differ from planned actual quantities shall be entered and other parameters will be adjusted. An example - if you entered actual activity volume of work, the software adjusts the remaining volume of work, actual and remaining duration, actual and remaining costs and material consumption.
You can modify actual data with the forecasts of remaining volumes, durations, costs, material requirements.
Entering actual and forecasted data you shall save this form to the specified folder, FTP server or just send it to Project Planner. Using command Consolidate monitoring data Project planner updates project model creating its new version. Previous version is stored in the project archive.
Reporting forms can be opened and filled with Spider Demo that is free. They can be exported to Excel and imported from Excel.
And of course you can create different access to the project data for different project participants defining what they can see and edit.
Best Regards,
Vladimir
Hi Rafael,
Sorry, I just want to lay down some facts as regards to your statements (if I maybe allowed?):
"Planning without considering resources is not good Project Management; it is hard for me to believe how some (isnt this ALL?) self proclaimed planners schedule their jobs without consideration for resources. I even have a few (again, ALL?) clients who do their initial “planning” without considering resources just to find out latter that their jobs are driven by availability of resources and then improvise"
Carlos,
Spider Project uses the concept of Monitoring Tables, because I am new at Spider Project and at the same time earning my food I have not explored this functionality yet. Vladimir can expand on this. Seems like you design and generate the monitoring document then you distribute it, maybe your managers might not need any special software to enter the data, in this case it is free.
From Spider Help.
Monitoring
Add Activities – invokes Include in monitoring dialog box to choose the monitoring Period and activities to be added to the Monitoring table.
Transfer into Project – brings activity monitoring data into the project.
Distribute Monitoring Data – distributes the monitoring data to managers assigned to phases by creating a separate document. Code of the created document coincides with the code of manager to whom the present document is distributed. A file with the document is kept in a folder or on an FTP-server (depending on the way of communication chosen in the User properties dialog box). The path to folder or FTP-server name set for the assigned manager, is displayed in the Users table.
Consolidate Monitoring Data – collects documents with monitoring data from phase managers. During monitoring data assembling from a folder or from FTP-server, the users specified in the table, get all (earlier not collected) last versions of the saved document from the moment of the previous consolidation. If there are monitoring documents of several projects in the specified site, the relation of each document to the certain project automatically is traced by the program.
Best regards,
Rafael
Raphael,

Regarding your statement about activity duration being unpredictable. Yes this is true but we still plan, better to have some course than none.
If you start from an efficient plan and one of your critical activities is delayed, your efficient plan will be delayed, on the other hand if you start with an inefficient plan and one of your critical activities is delayed your inefficient plan will also be delayed. Better a shorter and efficient plan delayed than a longer and inefficient plan delayed.
Another thing with resource leveling is that if your software does not gives you resource critical path you will get the wrong float, you will not know which activities are resource critical, you will be in limbo and at times will concentrate your resources on non resource critical activities.
The following simple plan shows four logic unrelated activities that if not because of limited resources could be scheduled all in parallel. Because Spider Project gives you resource critical float you can see which one is critical and how much true float has before its resources delay other activities. Other software such as Primavera P3, P6 and SureTrak will even show very long float for activities that are resource critical when in reality if you delay the activity a single day the job is delayed because of resource availability.
Planning without considering resources is not good Project Management; it is hard for me to believe how some self proclaimed planners schedule their jobs without consideration for resources. I even have a few clients who do their initial “planning” without considering resources just to find out latter that their jobs are driven by availability of resources and then improvise, forget about inefficient resource leveling they will do less than inefficient.
Best regards,
Rafael
This may sound out of place at this stage of the discussion, but what is Spider’s solution for collaborative work? P6 has something called timesheets but it seems you should buy an additional license for each timesheet and it requires some specialized work to properly configure.
I’m thinking in some feature allowing a manager to capture effort for a given period and actual production for that same period.
By the way, i forgot to say Hi.
Hi! =D
Rafael,
Spider scripts can be created recording your actions as in MS Office.
The script language is not the same as Visual Basic, it is described in Spider Project Help.
It permits to run Spider from other programs like ERP systems. Using scripts another program can launch Spider, open and update some project, schedule it and provide reports, import data and close Spider Project.
Spider Project includes direct import/export to MS Project and P4-P6. It also exports to mpx and imports from mpx. We use mpx for export/import to P3 but there is a problem with exporting materials - mpx does not support this.
You underestimate trend analysis functionality. Reports on the tendencies that exist in the project are very useful for decision making.
Spider Project Lite is not good for construction management - we aimed at IT managers creating this version. It does not work with multi-resources (crews of resources), does not simulate shift work (actually I dont know what software except Spider Project provides true simulation of working in shifts), it does not include multiple WBS and risk simulation. But it is very powerful and will easily work with huge projects.
For construction management I suggest to consider Spider Project Desktop. It includes everything that you may need (except portfolio management functionality, but you may work with multiprojects).
And I am sure that you will use many functions that now looks as too advanced with great pleasure. At least you will be sure that can model any project and any situation, can produce any report that may be necessary, and can rely on the project schedules and budgets calculated by the software. Besides, you will be able to create your own databases of different norms and project fragments and use them in your projects. With these databases the process of creating project model is easy and fast.
Best Regards,
Vladimir
Vladimir,
Does Spider use as script language Visual Basic? I dont do scripting using script language; I limit my scripts by recording steps like in Microsoft macros. Can this be done in Spider?
Because Primavera SureTrak is what we still use can I export P3 files from SureTrak and run my resource leveling in Spider? I suppose my layouts will not transfer but maybe WBS codes will keep order? Spider resource handling is so superior eventually my clients will notice. With the competitive price on Spider Light this can be the jump start.
Can Spider Light handle SureTrak? What is the limit on WBS in Spider Light? I am not interested on the Trends Functionality and would even like it out of my way; trends are too much for how we handle our jobs we try to keep it simple, to keep focus.
The other day Raf Dua told me, no single software fits all size of jobs, he is right, you also are right by providing true scalability.
Best regards,
Rafael
No, it is not included in the schedule report. It was there earlier but not anymore because the list will appear again and again.
The report can be created applying filters. For permanent use you can create the script.
There is a scheduling (leveling) option "Ignore preceding activity links if activity is in progress". You can switch it on and off. If it is unchecked then logical dependencies will be applied to the remaining parts of activities. Logical dependencies are considered first, only then other restrictions are applied.
Best Regards,
Vladimir
Vladimir,
Does Spider Project warns you about out-of-sequence progerss, is it on a schedule report?
What options for out-of-sequence progress you have. I got progress override and retained logic in SureTrak, none is a solution to the issue but the software gives you a warning and a report, then proceed the scheduling with either option as per your selection.
How does "Ignore preceding activity links if activity in progress " works, how about when unchecked? And what when no splits are allowed and you still got out-of-sequence progress?
Best regards,
Rafael
Click on lower bar left triangle to see video, you can also select the full screen option on the same bar, icon to the right.
Rafael
Where is the Resource Histogram?
The screen shots are a bit small, so I hope I can copy all the data correctly.
Cant do anything till tomorrow
Keep at it
Raf
Raphael,


I did took notice on Micro Planner Site how much they care about good resource leveling and also about keeping perspective.Yes with too much detail you lose it.
Here we say. Goes to the sea and cannot see water.
The following can give you all the data, it is a 10 activities scheduloe, dont waste time with WBS, I did it to learn Spider Project.
Remember you can run your own sensitivity analysis to see how resource allocation varies with your assumptions. In spanglish "what-if".
My regards to Lagrange multipliers.
Rafael
Rafael
Send me the data and I will put it through Micro Planner.
Mind you , you could do it too
Back last century, I gave up using Monte Carlo because as a technique it usually gives me the answer I was looking for.
Unless PR is different from the rest of the world, I think all the work you have been doing in proving Mathmatically a theorectical best solution in Resourcing is, with all due respect, a waste of time.
In fifty years I have never met (but then I have been everywhere at once) anybody who could accurately forecast the exact duration and absolute number of manhours required to execute a task.
My statistics over the years show that in my neck of the woods at least most Construction jobs performance is between 55 an 70% using EVPM as a measuring tool.
This project I am currently on is working at 80% because of the way we are driving the subbies, but so far at least fifty % of the sub contractors duration have been wrong, 9 out of 10 major subcontractors, so far after one year into our four project havent been able to man up their tasks over 60%.
I spent many years as a Operational Research scientist whilst developing ICT 1900 Series PERT and we did all this work using Linear Programming techniques, because as Vladimir says it takes a huge amount of time to do the calculations you need for an optimum answer, and one man/woman doesnt perform or turn up when scheduled , and you are back to square one.
It is a great intellectual exercise to do what you are doing Rafael,( I did my major educational accomplishments over thirty years ago in this same area.
But I have a project to run as close as I can humanly get to do what my Management and the Client want and need with the resources and money which arrive each day.
We use RFI cards to keep tabs on the trades to try and ensure that they work on the task allocated, but I know that the foreman will also manipulate my schedule to suit his purpose too.
The very best I have ever done on any project is to get 87% of my resources working and delivering work to the coal face. All done on Micro Planner Multi Sub Project Resource Scheduling.
Generally runs about four or five minutes for 10,000 tasks with in excess of 55 resource categories, plus all the EVPM computations as well and that was a Pentium IV
The sad thing Rafael, is that today nobody cares whether Product A is better than Product B, because if they did then these post would not be necessary.
Now I have to go back to work and alllocate where the time I have taken to respond to this post is to be accounted for.
See what I mean
:-)
Raf
From my posting 138
-"I am still figuring out in the 10 activities sample job you gave me what combination of prioritization can give me the same results as Spider Project. I also have to model the same again using Spider Project but not using your electronic file but my own without using driving resources. I suspect I will get the same results and Spider will again emerge as the winner, don’t take me wrong, just want to make sure as it seems too good to be true."
I modeled the sample schedule with my own file in Spider Project and got the same results.
CONFIRMED: SPIDER PROJECT IS BETTER THAN PRIMAVERA SURETRAK AT RESOURCE LEVELING. THIS IS NON-NEGOTIABLE.
Anyone willing to take Spider Challenge at resource leveling?
Rafael,
Yes, we decided not to use Monte Carlo for simulating risks in Spider Project for many reasons.
One of them – to achieve necessary precision you will need to make thousands of project resource leveling iterations. Usually our projects consist of many thousand activities. How long does it take?
Is your initial information on uncertainty distributions and probabilities of risk events accurate?
And most of all – do you need the accuracy or precision?
To be able to understand that you need to think about corrective actions it is necessary to analyze not the values but the trends of success probabilities. The trend 86, 85, 83, 81 shows that you have problem if your may rely on the data precision (next simulation will give the same results, may be not quite accurate but the same). Using Monte Carlo you need a lot of iterations to achieve necessary precision. And if your data are accurate but with 3% potential deviation you cannot decide anything by the same figures, It may happen the real trend was 84, 83, 85, 83.
Spider Project approach may produce systematic error that will be repeated but the trends are reliable. It may be that real trends are 82, 81, 79, 77. So what? You shall still think about corrective actions.
But our approach is fast, risk analysis is done every time when you enter actuals in seconds, trends are reliable and useful for management decisions.
Current methods of using Monte Carlo for project risk simulation are far from perfect. I already wrote that the initial data are never accurate. Activity durations are certainly correlated if they use the same resources, if risk events happen then the schedule changes because people apply corrective actions, resource assignments depend on the risk events, it is necessary to simulate risk events, not just uncertainties, etc. There are a lot of things that are missed if to apply Monte Carlo simulation as it is done in the majority of risk management software. And for large projects it does not matter much which shapes of probability curves you will select for individual activities.
In Spider Project you shall create three project scenarios:
Optimistic that includes only those risk events that will happen with 90% or higher probability,
Most probable that includes risk events with 50% or higher probability,
Pessimistic that includes all selected (in qualitative risk analysis) risk events.
These schedules may include different activities, resources and costs.
And probability curves are restored by three points for any project parameter (project and phase durations, costs, material consumption). The shapes are selected by Spider Project and may be not accurate for specific project. But the error will be repeated, so the next time the shape will be similar and the results though maybe not accurate will have necessary precision. If Spider trend is negative then the real trend is negative though probability estimate may be several percent higher or lower. We never have so accurate initial data to rely on the values. But we can rely on probability trends.
You will not be happy if the buffer will be visible when you submit your schedule to the client.
In the Gantt Chart you can always see both scheduled finish and target finish.
In any case the buffer may be shown only if you have the single project finish milestone that succeeds all project activities that have no successors.
It is easy to make it visible: Create hammock activity and call it project buffer, set its Finish No Later Than date that is equal to Target Finish. Link finish milestone with the buffer by FS link. That’s all.
But this buffer will mean that optimistic and most probable versions have the same finish dates that is not healthy for risk analysis. So I strongly recommend not to include this buffer if you really want to simulate risks.
If you will not use statistical analysis then add buffer but create the WBS structure that is not full and exclude buffer activity from this structure if this version will be submitted to the client. In this case you will see the buffers in one structure and they will be hidden in another.
I did not understand what you wrote about entering actuals with three project scenarios.
These scenarios may use different resources, links, costs, include additional activities, etc. But in all three scenarios the actual data will be the same if you entered these actual data in one of them. The remaining durations of the started activities also became the same if you will not enter some changes manually. We usually work with the models where activity durations are short and those who began the work can estimate what is left better than anybody else. But if activity is not finished manual adjustment of remaining duration is available. I don’t understand what did you expect.
Best Regards,
Vladimir
Spider Project calculates time buffers, cost buffers, material buffers necessary for achieving project targets with user defined probabilities.
These buffers can be calculated for the project and different WBS phases if the targets are set not only for the project but also for separate phases. The calculation is based on risk simulation.
Project time buffer is the difference between scheduled project finish and the target finish date. Actually it is project completion contingency reserve.
We recommend to use optimistic schedules and budgets for setting tasks to the project workforce. Buffers shall be used by project management as reserves for project risks and uncertainties.
It is natural that during project performance some activities are late and more expensive than was planned in the optimistic scenario, so project buffers become lower. It is necessary to have some buffers left when the project will finish.
So there is a need to estimate buffer penetrations - are they still sufficient for achieving project targets or meeting project goals is endangered?
Buffer penetrations are estimated by risk simulation of remaining works and estimating current probabilities to meet project targets. If the probabilities became higher then our buffer penetrations are lower than expected, lower success probabilities mean that we perform worse than expected. But not only this can cause problems or benefits.
Let’s suppose that we have done everything properly but new risks were discovered. These risks will change probability distributions for project duration, cost, etc. And though performance was good the probabilities to meet targets may go down.
So probabilities to meet targets (Success Probabilities) take into account all project data including risks and are really integrated performance indicators.
But we recommend to pay most attention to trends:
If probability to meet project targets is not high but rising it means that the problems that existed in the past were overcomed.
If the probabilities are high but going down it means that the problems exist now and it is necessary to consider corrective actions.
So Success Probability Trends are really good integrated performance indicators that include scope, schedule, cost and risk performance. If to supply top management with success probability trends it will be sufficient information on current project situation. Projects with negative trends need attention.
Usually we set not one but several project targets - one for the project management team that includes contingency reserves, another one for top management with additional management reserve. The third set of targets is defined by the contract. Success probabilities will show what happens with all these targets. Success probabilities trends may be negative for PM Team Targets but simultaneously positive for top management targets. It means that the chances to meet PM Team targets are lower but management reserve is sufficient.
Best Regards,
Vladimir
Vladimir,
How do you manage buffers within Spider Project?
Best regards,
Rafael
Vladimir,
"some other features like showing material consumption not only in columns but also in the rows like assignments"
I always dreamed about this, you already know:
I WANT TO KNOW ON THE SPOT WHAT IS DRIVING MY SCHEDULE.
Best regards,
Rafael
Yes, you are right and different Spider Project customers create the schedules paying most attention to different sides of the projects.
I agree that the option to hide or show the sets of options (resources, costs, risks, etc.) is useful and its development is already in our plans. But before that we will taught Spider to work with conditional networks (if ... then) and add some other features like showing material consumption not only in columns but also in the rows like assignments. We never stopped the development.
Best Regards,
Vladimir
Vladimir,
When I mention the idea of switching off and on sets of functions for ease of use I do not mean I will never use them. The use will depend on the particular job and purpose of the schedule. In my particular case I do not need the network functionality but would like everything else. After you give a boy a candy you are not going to take it away.
It is not the same a schedule for construction purposes where I would go into more activity details and resource loading than if a schedule to analyze a job for a Real Estate Development firm, here I would not get into resource loading and would use less activity detail but would use cash flow and financial investment ratios.
Best regards,
Rafael
Rafael,
yes, we plan to do it but we have not this options today. I think that this feature will appear in 2010.
Scarlett,
we recommend to analyze the trends of important parameters, not just values.
In Spider Project you set project and phase targets (dates, costs, profits, etc.) that can be achieved with reasonable probabilities. And then the software recalculates success probabilities each time when project data are changed (if you entered actuals, if you added mitigation activities, if you discovered new risks, etc.).
The trends of probabilities to achieve project targets we consider as the best integrated performance indicators. If probabilities to meet project targets decrease it means that corrective actions shall be considered. This approach works if you apply risk analysis to your schedule.
If you do not analyse risks and work with deterministic project schedule you still shall analyze trends - trends of the total project duration, trends of the total cost, etc. If the forecast of project duration is rising you shall consider corrective actions even if the project is ahead of the schedule.
So Spider Project calculates and shows trends of any project parameter.
Performance analysis is done on the data that was entered in Spider Project. If rejections and accidents were entered then they can be analyzed.
We recommend to create Responsibility Breakdown Structure, Organizational Breakdown Structure, Process Breakdown Structure and Resource Breakdown Structure. Reports generated in these structures show:
1) Performance results by responsibility areas and Departments,
2) What processes caused problems,
3) Performance of resources.
If you entered the number of accidents and rejections then you will get reports on their numbers by Responsibility areas and Departments and their distribution over time.
Best Regards,
Vladimir
Scarlet,
A few days ago you mentioned how overwhelming can Spider Project be with so much functionality. I believe for the majority of jobs I do you are right, just for a very few I would need all Sipder Project functionality. To make easier to navigate in Spider Project when you do not need so much horsepower Vladimir said “We plan to create a version where our users may decide which functions to hide. It will make Spider interface adjustable”. I just hope this becomes a reality soon as it will only switch on the turbo when in need of 1,ooo horse-power, and then the NOS when in need of 3,000 horse power.
About Pacquiau–Cotto fight you know very well how good Pacquiau is, while Cotto is not the same after his fight with Margarito. Can you raise the stakes up a little; say 100 to 0 instead of 50 to 0 so I can start consider the bet?
Vladimir,
Can the hide functionality be applied to related sets not on an item per item, as to make it easy to toggle on and off?
Best regards,
Rafael
Actually what Im trying to say
The goal of a basketball team is to win
The goal of a project is to win
But of course they have different parameters.
On the other hand, basketball team got: team manager, coach, and staffs
while projects got project manager or project directors, construction managers and staffs.
Basically, the staffs prepared relevant and pertinent information for the managers to acts to achieve the goal.
So, I think planners are also involve in statistics.
If you can share how Spider help the planners by maybe providing customize reports that captures important parameters in view of the tremendous information generated from planning software.
Also, what important parameters are usually track. I think this is now becomming basic, but, somehow, it is not happening in our projects.
Thank you,
Scarlett
Hi Vladimir,
Im in the middle of 2 billion ++ US dollars project and Im frustrated since, somehow i feel, our planning group are not fairly treated.
In this state a lot of wandering of the mind will happen.
so I just thinking if project team can be run like basketball team or whatever sports.
Basically, Im looking at the aspect of planners being the statistician.
For example in baseketball, it is the most popular sports in our country, the opposing team or most of the times the media presents statistics: numbers of rebounds, turnovers, fastbreaks, etc. etc.
From the statistics, it is very easy to have a clear understanding of the winning team even though the games still in progress.
Question: have it occur to you?
Because now Im preparing statistics like for example: actual periodic accomplishment, number of rejections, accidents (safety issues), etc.
from this actual statistics, it may help in evaluating future performance and how to acts on critical issues.
Is Spider very specific on what to look at from the myriads or tons of garbage data.
Thank you,
Scarlett
Hi Scarlett,
I want to remind that I proposed to suggest hard tasks, something that most or all packages cannot do. I will answer if and how it can be done in Spider.
So this thread is open for anybody who may ask questions like how to do this or simulate this, etc. If Spider can do it or not?
So it is about beating Spider, not Vladimir (I hope).
Do you have some hard task to propose? Does your software everything you need?
Best Regards,
Vladimir
Hi Rafael,
Im glad to be honored a genius from someone like you, the most genius of all.
I do not know how to paste movies in PP or any brilliantly colored charts, etc.
So in reality, you are now the most genius here in PP.
By the way, I just find it strange that in previous threads, you almost wanted to beat Vladimir and ask the help of Mike.
Now it seems you and Vladimir are BFF.
Strange isnt it.
Since Mike locked the previous thread, we can continue the Pacquiao vs Cotto here. What do you think? It is still 50 USD to 0.
Thank you,
Scarlett
Rafael,
thank you for the movie.
I like your demonstration, it looks like people enjoy it.
Best Regards,
Vladimir
Rafael,
usually it is done different way.
Spider Project permits to create different Reference-books (databases) and use them in your projects.
These Reference-books usually include Resource or Crew productivities on typical assignments, material requirements on different activity types, unit costs, etc., no restrictions. Usually people create one project model but three sets of reference-books (optimistic, most probable, pessimistic). If you apply pessimistic set you will get pessimistic scenario, applying most probable you will get probable scenario and applying optimistic you will get optimistic scenario.
Reference-books make the process of creating project model much easier. If you enter activity types and work volumes then reference-book will add material requirements, costs, durations. If you will assign some blank crews reference-book will fill them with resources, productivities, costs.
Pessimistic scenario can have additional works (risk events may happen) that in optimistic and most probable version have zero duration and costs. Some works may exist in both pessimistic and probable but absent in optimistic.
So one project schedule can be easily transformed into three project scenarios and then the software will synchronize them when actual data are entered. The actual data are the same and you shall enter actuals only once. But if the scope will change you shall apply reference-books again and save the results as optimistic, probable and pessimistic scenarios.
Any changes in reference-books can be easily transfered into the projects that use this information. To do this it is not necessary to open Reference-books, that are usually maintained by PMO, just give the command. But it is not done automatically because Spider Project keeps project archives. So Spider Project users create project versions 1, 2, ..148, etc. and you will not want to apply todays reference-book if you opened project version created 6 months ago. Any two project version can be compared including optimistic with pessimistic, etc.
You can use several parallel costs (and cost components) for the same activities and resources and will get reports on project expenses and earned value (contractual) in parallel. Of course internal costs are not submitted to the Client.
I am glad that you like Spider Project.
Best Regards,
Vladimir
Vladimir, yesterday we had a public demonstration due to government payroll reduction. We have our share on this recession as everyone else.
Best regards,
Rafael
Vladimir,
Do the different versions share the same database structure. So that whatever I create in one version the other will be able to see, but only the fields avilable and operate within available functionalities while keeping untouched the other fields.
That is, full upward compatibility but limited downward visibility.
I kind of like Spider Project Desktop (one user version)
as it seems the best fit for my needs. And the price 1,000E is very competitive.
Best regards,
Rafael
Pagination