Wizard......

K
Ken Sadler 👤 Member for 17 years 10 months
R
Richard Ormerod 👤 Member for 17 years 11 months

Ken



This is almost always down to restricted access to the \Project \Template folders in the install folder.

Change these to Full Control and you should be OK.



The one advantag eof the Template route (rather than Mike’s Copy/Paste) is that it sets "Week 1" on the Date Zone in all Views of the project.

Just saves you a little hassle at set-up time.

M
Mike Testro 👤 Member for 20 years 5 months

Hi Ken



I create a standard bar chart for a particular type of project with set up calendars - resources - work patterns etc.



When a new programme is required I just copy the chart and save as required.



Then adjust for the new start dates etc and start adding tasks.



I never use the wizards but set up a bespoke base evry time.



Best regards



Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts