NUMBER OF ACTIVITIES

F
Forum Guest 👤 Member for 17 years 4 months
P
Philip Jonker 👤 Member for 21 years 7 months

Hi Alex,



The tilos report is just another report, and the quality is dependant on the amount of thought you put into what the picture should be.



Regards



Philip

A
Alex Wong 👤 Member for 23 years 3 months

Hi Philip



Welcome back, I had seen the Tilo product and its quit good in terms of the graph that is produce and the interface package. My question is whether summary(hammack) bar will be correctly represent the programme. Especially with the interface between differernt parties(Contractors) within an single area.



My point is not so much about the software but more on technique use in planning. Agree??



Alex

P
Philip Jonker 👤 Member for 21 years 7 months

Hi Guys,



If you see a diagram you might understand the concept, True linear activities (eg. continuous activities such as tunnels, trackwork, lateral drainage, finishing layers, viaducts, etc) are shown as sloped lines as the time is vertical and time chainage axis horizontal. Non-linear activities (or activities that is spread over a limited chainage eg. stations, shafts, culverts/utilities crossing the centre line at right angles, etc) is reflected as vertical bars, with the various sub-activies stacked within the bar. For Linear activities such as cuts and fills, where the work is spread over longer chainages (over the whole chainage) we use triangles. The reason for this is that you can use the direction in which the triangle is pointing to indicate where the cut is going, or where the fill is coming from. We use straight horizontal lines to indicate activities such as accesse over certain chainage distances. The beauty of it all is the you can spot clashes or incorrect logic very quickly, and make your corrections in the schedule, something which is much more difficult to spot in in ghantt chart of 200 pages.



Daniel, you are quite correct in that all you are doing is using height instead of chainage, hence, the term line of balance is probably more applicable. However, the symbols you use to depict activities still have to be picked correctly to get the right effect. It may also be interesting to use the horizontal axis for time and height vertically, as this can be done fairly simply. I find that these diagrams are very simply understood by all other disciplines, as the use of colours, patterns and outlines, can depict types of activities, resources etc.



Regards



Philip

D
Daniel Limson 👤 Member for 24 years 7 months

Philip,



Although the scheduling technique is similar, Line of Balance is more applicable to vertical construction or high rise buildings and repetitive tasks where there is a lot of interface between trades, say works such as construction of a village with 100 houses. Time Chainage on the other hand is good for horizontal construction, Roads, Bridges, Viaducts, Tunnels, Railways, etc. where you can plot your work chainage against time.



Cheers,

Daniel

V
Vladimir Liberzon 👤 Member for 25 years 4 months

Hi Philip,

glad you are back.

What you described is hard to do and produce results that are not quite correct. Hammocks will be represented by straight lines though on activity level the shape would be different. Maybe I don’t understand something.

Regards,

Vladimir

P
Philip Jonker 👤 Member for 21 years 7 months

Hi Guys,



Been absent for a while. There a several Line of balance or time vs chainage programs available, however after a serious evaluation, we decided to go with Tilos, a german product. I work in a joint venture company, international, on a linear works project. We use Primavera Project Managemet V5.0, and as a result had to find a product with the least finicky interface from our Primevvera schedule, to produce LOB or T vs Ch diagrams. It took a bit of thinking to get the process right. Firstly to try and produce the TvC diagram directly from P v5was impossible,as the number of activities cluttered te diagram to such an extent it was totally illegible. The question was how to export summary activities to Tilos in a form it could read without the minor detaild. The answer was simple, create a hammock (level of effort project) and export from there there to Tilos, the Hammocks had to be coded as per normal procedures, and voila we had a beautiful line of balance diagram, for anybody who is interested contact me. I can send you a PDF of what it looks like. It just requires a bit of lateral thinking.



Regaeds



Philip

D
Daniel Limson 👤 Member for 24 years 7 months

Clive,

Sorry for the late reply..I only open my email once a day.



anyway, 6 months ago when we were looking for a good "line of balance software" Grahpisoft Project Control 2005 was the only one we found in the internet, which corresponds with our needs. (Previously called Dynaproject)



Actually, we just started using it and had undergone training recently.



You were quite right in your brief view of its usage. It is like a time chainage in vertical position, which is good for high rise buildings or repetitive works where there is a lot of interface between various trades.



In addition to what you have said. The sofware requires quantities and production rates defined which will be the basis of your plan. Actual production on site is then monitored. The flowline view (line of balance chart) is an excellent tool for managing the project ilustrated on a single chart. You can then adjust your resources base on your actual production rates to bring it back on line. The beauty of it is that at any point in time you know where every trade is working and how they are doing by just looking at single chart.



The software has many features and includes reports and status of tasks which maybe be discuss in progress meetings of the construction team who are actually doing the work.



This is all for now, I might be mistaken as a Graphisoft representative.



Cheers,

Daniel


D
Daniel Limson 👤 Member for 24 years 7 months

There is only one Line of Balance software in the market today. The software was produced by Graphisoft of Finland.



We are currently using it on the Venetian Project in Macau. The software is good for high rise buildings or repetitive tasks.



You can browse the internet and look for Graphisoft.



Cheers,

Daniel

B
Brij Patwari 👤 Member for 21 years 9 months

Hi Clieve,

UR post seems making sense..

But a bit difficult to understand for me.

Can u eloborate?

Regards,



Brij.

J
James Griffiths 👤 Member for 20 years

Edgar.....ouch!! That remark about "....has gold...breaks rules...". It has just hit a really sore point. We have a client who has done that....and all I can say is "kill, Rover, Kill....just bite his leg off and chomp your way up through his left bo**ock".



It was all politics. Unfortunately he’s paying our wages...so is it a case of Nuts to the professionalism and just bow to the politics? Oh God, do I have to compromise my principles, just to feed my children?



Oscar: Agreed. Like anything else, lots of it doesn’t mean that it’s any good. I like to minimise my workload but I also like to have a good handle on the job. If 500 does the job, then 500 it’ll be. By the way, could you expand on the term "Line-of-Balance". Although I’m fully au-fait with the term in manufacturing, I’ve not come across that one in Project Planning.



Cheers.



James.

E
Edgar Ariete 👤 Member for 20 years 10 months

or is it, He who has the gold, breaks or burns the rules? now ACT, ACT, ACT...

O
Oscar Wilde 👤 Member for 20 years 8 months

James good point

However

Often I see the same group copied and pasted across the entire programe in an effort to break a record

Complete worthless c**p and often better done on a line of balance now their is a thought

Oscar

J
James Griffiths 👤 Member for 20 years

Hi to all you you on PP. I’ve just come across this thread, owing to the fact that I’m new to PP. It was so interesting that, instead of doing my work, I just had to go back to the beginning and "read-all-about-it".



Great discussion; excellent viewpoints and experiences. It just goes to show that "planning" is a combination of an art, a science, management philosophy and contract definitions. There is no Golden Rule (as asked in another thread) other than the reply to said thread, being: "He Who Has The Gold Makes The Rules".......brilliant!.



With regard to the number of activities in the schedule: My basic philosophy is: "The level of accuracy and detail to the answers, that you wish to extract from the programme, is proportionate to the amount of time and money you wish to spend on the planning function". KISS(ing) the programme too far means that you’ll save money on the planning/administration....but also you limit the detail and accuracy of the data. Conversely, too much detail and the administrative burden becomes overwhelming. The word OPTIMUM is the order of the day.



Ultimately, I suppose that the real test of the programme’s function is the accuracy of prediction relative to what actually happened. Without being too much of a smart-alec; I detailed my latest project from a basic 800 lines to 4000, running 30,000 manhours over 18 months. In our company, such a project size is not unusual, but the use of a 4000 line programme is unheard of. At 800 lines, on the Tender Programme, it looked achievable (I hasten to add that I wasn’t involved in the Tender Programme). At 4000 it was instantly obvious that it wasn’t achievable. Unfortunately, the budgets/contract had already been agreed. We were in for a really good stuffing!



During subsequent execution of the work, the programme has accurately predicted (relatively speaking) drawing-checking bottlenecks 9 months ahead of schedule. In our business, such a forward projection is pretty-darned good to correctly predict that level of detail so far in advance. Unfortunately, the company’s philosophy toward planning is one that is much more geared toward paying it lip-service than heeding its advice. It’s now paying the price!



I have stood-by my programme since the project. My PM knows that I will stand by the programme and argue with him, because it is derived from detailed discussion with engineers - and he is welcome to investigate any aspect of it. He wants to ignore the data, as would any other PM. However, he also realises that good data is invaluable and that there is no point in kidding himself. The data, however, is utterly useless and a complete waste of money if no action is taken.



All of the above is based on getting the right level detail. If it takes 500 or 50,000 activities, it is irrelevant. The question is: Are you professionally satisfied with what you’ve done?



I really do have to get back to work now.



James :-)

O
Oscar Wilde 👤 Member for 20 years 8 months

KISS KISS KISS

for those that dont know

this means keep it simple stupid

E
Edgar Ariete 👤 Member for 20 years 10 months

Henk,



just curious why you keep using "bid" instead of bit? would that mean you’re more concerned about costs rather than details?



thanks

H
Henk van der Heide 👤 Member for 21 years 10 months

Edgar,



Many times a milestones means an (important) start point or end point for a group activities. At least thats mostly the case in my schedules. So the total progres of this group of activities tells you someting about the progress of the activities how are leading you to the important milestone.



On the other hand If you use The milestone for example as an KPI (Key Peformance Indicator) and you measure by total float or time variance (against baseline) it also tell you something about the progress of the activities who are leading to this milestone.

This type of report (KPI) is used a lot for Management Reports.



Hope explaines a little bid.



Kind Regards



Henk

E
Edgar Ariete 👤 Member for 20 years 10 months

Henk,



I don’t understand. Would you mind explaining further?



Best regards,



Edgar

H
Henk van der Heide 👤 Member for 21 years 10 months

Edgar,



I think the progress of a milestone can be measured by the progress and total float of his predesessors. ?? (assuming that the milestone is fixed)



Ok the answer is a little bid deep, however i think it could be treu.



Kind regards



Henk


E
Edgar Ariete 👤 Member for 20 years 10 months

Everyone in the project team needs a clear, honest & reliable information irregardless of which side he/she is working.



The question here is what is the ideal total number of activities for a certain project? Say, a typical high rise building or a road construction? An engineer or a planner who knows how to build inside-out is supposed to understand the basics or the sequencing of the tasks & to organize the program as to produce the desired result.



I agree that there is no definite answer for getting the exact total number of activities (tasks) as each & every project is unique. Now, how can a program becomes measurable? Is it necessary for each & every task to be measurable? And what is supposed to be the ideal unit of measure? Or milestones enough & accurate to measure a project?



Oh, by the way, how is a milestone being measured?

V
Vladimir Liberzon 👤 Member for 25 years 4 months

Se de leon is right.

There is not a need for the detailed schedule if

1) you are on Client side,

2) your resources are not limited and the task of resource optimization does not exist.

My example of 3000 activities for 11 floor building construction project was taken from the real life contractor’s schedule. The schedule was used to estimate the optimal amount of frames to be used and the number of construction workers that are needed.

Best Regards,

Vladimir

S
Se de Leon 👤 Member for 25 years

Hi guys,



Hi Walied. Are your working for the contractor or consultant/client side?



For me this question really depends on how you view project management culture in the organization you are working for whether resource allocation is a primary concern in coming up with an execution programme or if the only concern is the project strategy/achievements.



For example, some contractor’s project managers will require his planners to go deeper into resource optimization as what vladimir said. If this is the case, then most likely the activity number will increase. Some contractors doesn’t do this. Some consulting planners require such recource management outputs from the program. Some contracts requires such resource optimization and risk analysis.



To answer again the question, it really depends on the Proj. Management culture.



Just my 2 cents.



Hope this helps.



Se

W
W A 👤 Member for 20 years

Sorry, still not agree, i am doing all what you are saying wihout too much subdividing.



My methodology is the programme is a managment tool, not site tool.



However, I respect the difference in points of view.


V
Vladimir Liberzon 👤 Member for 25 years 4 months

If you use the software for resource usage optimization you will need to create the model that simulates actual activities on every villa in your project. Actually it is easy because you can use templates.

You will also need the detailed schedule of materials utilization to optimize supplies.

So you will need to create new activity each time when the character of work is changing (different resources, different materials, different productivity, different cost, different calendar).

Such model can be used for resource (and supplies, and cost) constrained scheduling and risk analysis.

You described high level tracking of project execution. It is different task.

Regards,

Vladimir

W
W A 👤 Member for 20 years

Vladimir,



I am currently working in project of 110 Villas, with only 1300 Activity, include material & Shop drawings submittals, and Procurment. every villa is 3 floors, include soft and hard landscaping, boundary wall, and of course external works of the site it self. the project is $50 million.



The monitoring and control of the project is smoth and very effiencet, i would like to mention that at any time i can see exactly how many villa is completed and how many was planned by that time and also the number of the villas, (such as villa 44, villa 45, etc..), without the need to make seperate programme for every villa, just making zones.



From project management perspective, making too much activities will make the project team managing the schedule instead of managing the project, this issue is addressed clearly in the PMBOK of PMI, and in any project management book.



Walied Abdeldayem, PMP

V
Vladimir Liberzon 👤 Member for 25 years 4 months

Walied,

my experience shows that the model for construction of one 11 floors building consists of approximately 3000 activities.

Nobody will create more activities than necessary for proper modelling of resource work.

93000 is too large for one ship, but unfortunately the same Ship Yard resources are used for different ships construction. As the result you need to plan all of them.

For your information:

The model for construction of one ship body consisted of 11000 activities.

Regards,

Vladimir


H
Henk van der Heide 👤 Member for 21 years 10 months

I think i agree on that.

One of the worst things that can happen is planning one level to deep. What means that the project will not use your planning anymore because they cant read it. And it means for the planning engineer that he gets the progress on one level higher than his planning so he has a lot of work translating the progress into the planning.



So better try to keep the planning as simple as possible and try not to see it as a product it self.

Of course the planning needs to have the details so you can use it for the control. So it always comes back at the point that the structure must be ok and the level of detail must be ok, and for me this is never the same. (planning is not that easy)



Kind Regards



Henk




W
W A 👤 Member for 20 years

93000, 35000, 11000 !!!! what is that !!! guys we are modeling the project not more than that, MODELING !!!



making lareg number of activities (more than needed) violates the spirit of project management and planning. The minimum activities you got the moew effiecient you be, we are not making method statement in the programme, the project engineer and the formen know what to do.



I belive that the programme is a MANAGEMENT TOOL, it should be the link between the reality and the decision makers, just keep it that simple you got better life.



The rule of thump in decomosition the activities is untill you can assign one man or one group to do it, if you sub-divide more than that you got more activites than you should. I do not see any bad thing to say in the progress meeting that we achieved our plan in this week, and we have 10 acitivites done by 70%, or such like, What is the benifit to say that we have completed 200 activity in this week!! the execitives will only concern about overall planned, and overall actual perecentage.



From my experience in construction, 700-2000 activities are enough, not sure about the ships project though, but i am sure 93000 activities are just too much over the optimum.

S
Svein Myklebust 👤 Member for 20 years



A large number of activeties does not realy mean anything else than a large number of activeties.

It tells nothing about the level of control the managemnet got.



The goal is to get the right activeties into the schedule and

keep a structure that fits the rest of the project.

To many activeties can lead to a project within the project

and therby planning to be a burden and not the tools it’s supposed to be.



s

I
Izam Zakaria 👤 Member for 20 years

talking bout.... number of activities.....i had running around 11 000 activities......may I’ve ur prx file?

P
Paul Silver 👤 Member for 21 years 8 months

Sen,



The largest number of activities in a schedule I have run is around 40,000 with 60,000 logic links and 80,000 resource assignments. The job was for a maintenance turnaround in a nickel refinery, took six months for two planners and one planning assistant to prepare. Feed off to feed on was twenty three days which meant progressing an average of about seventeen hundred activities per day. Progress data entry was done via an Access Database front end on P3 by the planning assistant whilst the planners gathered the progress information in the field. (I don’t generally trust the supervisors to be completely truthful where progress is concerned)



Regards



Paul Silver

S
Sen Moc 👤 Member for 20 years 9 months

Now going back to topic, may I post this question again:



WHAT IS THE MAXIMUM NO. ACTIVITIES EVER DONE SO FAR? And what type of project is this, why this big number? How was it done?



In Post #5, it was stated that a 93,000 activities was provided for a shipbuilding project. Are there other projects exceeding this no?



Sen

D
Daniel Limson 👤 Member for 24 years 7 months

We should be starting a new thread, as this is no longer related to the above subject. However, In addition to Sen’s post, I agree that we should be reviewing logic on a regular basis in line with the workflow on site and the availability of resources to make it a more realistic schedule.



In construction or whatever task it maybe. You have this inherent logic which you can not change (progressive way of doing a task) and the preferred logic or workflow (your preferred means and ways of attacking the work). The workflow should be agreed with the construction team and this should be done considering the availability of resources.



Regards,

Daniel

S
Sen Moc 👤 Member for 20 years 9 months

That is correct, Joel. Logic review, analysis and updating are part of the schedule progress updates. And I’m referring to the CURRENT Schedule not Baseline. I’d say the Logic should be reviewed, analyzed and updated because Project Team including the client are monitoring the project finish date. Without changing the logic, a lot of activities are becoming out of sequence, thereby not showing the true calculated total floats or project finish date – just as I’ve stated in "Changing the logic when project is underway" topic.





Regards,

Sen

J
Joel Gilbert 👤 Member for 23 years 1 month

Hello Sen,



Did I see you mention "Logic review", You better not mention that. You will get all sorts of questions. Did you not follow the topic "Changing the logic when project is underway"



Hey don’t worry, as I’m in the same business I understand.



Regards,



Joel

S
Sen Moc 👤 Member for 20 years 9 months

Project: LNG Plant(2 Trains)



Scope of Works: EPC (Engg, Procurement & Construction)



Duration: 36 Months



No. of Activities: 3000 (at Level 3)



Software: P3.1



No. of Scheduler: 1



Takes 3 days to prepare monthly progress update on P3 schedule including logic review, analysis and update.

J
Jorge Taguinod 👤 Member for 22 years 11 months

I understand your point, Sen. But then again, this is relative. I can’t expound on a rebuttal since doing so would bring me out of topic.



But your point of view is well taken.



Thanks,



Jorge

S
Sen Moc 👤 Member for 20 years 9 months

Agree with you Jorge, but not on this one:



"Again, it boils down to: Fast, Cheap & Good -- pick any 2."





I think there’s no option on the above statement. It should be FAST, CHEAP & GOOD.





Cheers!

Sen

S
Sen Moc 👤 Member for 20 years 9 months

Guys,



From the more than a hundred posts on this subject, it is evident that the No. of Activities VARIES depending on so many factors such as project size, type/classification, planners involved, etc…



For the record, WHAT IS THE MAXIMUM NO. ACTIVITIES EVER DONE SO FAR? And what type of project is this, why this big number? How was it done?



In Post #5, it was stated that a 93,000 activities was provided for a shipbuilding project. Are there other projects exceeding this no?



Would be glad to know.



Regards,

Sen

R
Rolyn Jalea 👤 Member for 22 years

Good post Jorge....



I think no. of activities will vary from one project to another, from one discipline to another. say, we can’t expect roadworks to have more activities compared to building works or power plants.



It will all boil down as to what extent you need your programme to be detailed to suit your requirement & your client’s as well.



Regards



Rolyn

J
Jorge Taguinod 👤 Member for 22 years 11 months

I really think that the number of activities is derived from the desired level of detailed needed by the stakeholders. More detailed levels will increase the number of activities. And a bigger project will also increase it.



Now, the question is, do we bug the people who execute the works to submit reports? Will they be more productive doing what they’re good at (Executing)? If so, I guess controlling (i.e. collecting project progress info) should be left to project control. This then increases the staffing requirement for people who would monitor/control the project.



After reading what has happened (project performance analysis), the replanning part should involve the people who owns the work (the people who execute). I don’t think that planning should be left to theorists -- the people who will execute the work should have the largest say about how it will be done. They, after all, are accountable for their piece of work (WBS).



Bottomline, we need to perform a Needs Analysis answering the question: How detailed is the planning requirement as demanded by the stakeholders? Then we staff it or go into project procurement if we want to outsource this piece of work (planning and controlling, managing the project information system). Lastly, we ask ourselves: Is the resulting cost needed to deliver the need justifiable? If so, no problem. If not, we need to either improve the system to minimize resource requirements (for the PMIS), or sacrifice quality.



But then again, sacrificing quality might prove expensive in the long run. Even managing the PMIS should be planned (obviously). Again, it boils down to: Fast, Cheap & Good -- pick any 2.



Ideal, huh? Doable? Depends on the leadership. And the budget.



Best regards,



Jorge

J
Joel Gilbert 👤 Member for 23 years 1 month

Interesting debate.

To stop the argie bargie and put us back on track.



How does a planner monitor 40000 activities on site? Or has the old planning concept changed ? and now we are supposed to be desk bound data capturers. The fun part was always to steer the job on site, getting involved and making sure everyone works to the schedule.



What’s the forum opinion?

P
Philip Jonker 👤 Member for 21 years 7 months

Hi Oscar,



From reading your posts, they do not impress me, did you sleep with a planners sister? This vast experience you have must have stemmed from there.

O
Oscar Wilde 👤 Member for 20 years 8 months

I Like the first part



however does anybody on site plan???

are the foreman robots

are the site engineers moluscs (SP)

is the site agent oh never mind



plan 400000 activities nonsense

3 day duration drivel

total total nonsense

its not planning its bar chart generation



planning

to endeavour to work out the the smallest number of activities that have to be completed and to successfully demonstrate what activities need to be completed in longest logical sequence to complete the project in the shortest possible time and in the most economical manner.



40000 bars of nonsense sitting on the wall one went wrong and they all fell off

J
Jorge Taguinod 👤 Member for 22 years 11 months

The number of activities in a project depends on:

1. the size of the project

2. the complexity

3. the level of detail needed by project stakeholders

4. the type of industry (mining projects tend to have less detail than fabrication or refinery turnaround projects)

5. the number of competent planners available



Coming from the construction industry, i believe that an activity should have a duration of about 3 days. I have planned a design schedule for the construction of two whole cities (from the ground up). The design schedule alone came up to 40,000 activities. Updating was done using Primavera Post Office. It was fully resource loaded and was integrated with an accounting software. The whole schedule took 1 ream of A4 to print.



However, one does not really have to print the whole schedule during the execution and controlling phases. Lookaheads suffice. And during updating, we just check if the milestones are met. If not, we try to comperss the schedule and look at the resulting resource loading, and cost curves.



It is really not a matter of having thousands of activities. I think that the quality of the schedule should not be sacrificed by developing a high level schedule. Detailed planning is very important. For it is only through detailed planning that you really get to know how to go about executing it -- considering all the design works, procurement schedules, staffing, and actual execution (constructing, installing, testing, etc.).



So if you have a large complex project that needs a lot of activities, make sure that you have sufficient staffing to take on the planning and controlling works.



And I was just talking about the work P3 entails. When you go into Primavera Enterprise, you would need much more peope beucase this piece of software can really address a lot more project management information such as project expenses, risks, etc. Moving from P3 to PE is like upgrading from Microsoft Project to P3.



I’m working on a minesite development project with no smeltering equipment. So the schedule is really simple. Under 200 activities. Very relaxed. Problem is, the people in the mining industry is not as well versed in project management as construction people.



Oh well...

O
Oscar Wilde 👤 Member for 20 years 8 months

Charlie



Please answer David



He has asked a valid question on what appears to be games theory



Oscar

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts