Resource Allocation & baseline

M
Mike Testro 👤 Member for 20 years 5 months

Hi Asadullah



You assign resources to an activity in a programme.



You have to have the activities in place first.



When putting together a Bottom Up programme I set the durations at "best guess" based on my experience.



I then set up the resource modelling software to take the work load for each activity and the appropriate gang size.



This generates a resourced duration that over rides my original best guess.



Make sure that the resourced programme complies with your start and end dates in the contract.



This would represent your Planned resources.



If the work load or gang sizes change during progress you can change the resources in your baseline to replicate the anticipated effect on progress.



I hope this helps.



Best regards



Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts