"ns" in predecessor / successor columns
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
ns means the task that is linked to/from is "not shown" in the current view, usually due to a series of tasks being collapsed from view or the task has been marked for hiding.
My friend
You can find complete tutorial in youtube, or you can have them free from ASTA
Regards
Razmik Aslanian
Hi
I may be wrong but I think it means the predecessor/successor is not started.
If you look at the properties for a particular task (right click on a bar and select properties) and then look at its links, it gives you the progress for each predecessor/successor.
Regards,