remove links between % completion and budegted quanty

B
bilal tirmizi 👤 Member for 17 years 5 months

THANKS FOR THE REPLY DB



I HAD ONE MORE DOUBT:





I WANT TO REMOVE LINK BETWWEN UPDATE PERCENT COMPLETE AND ACTUALS QUANTITY TO DATE BY UNCHECKING THE RULE "USE THE UPDATE PERCENT COMPLETE AGAINST THE BUDGET TO COMPUTE ACTUAL QUANTITY TO DATE." AS I AM THINKIG THAT MAY BE MY ACTIVTY IS 10% COMPLETE BUT THE RSOURCE THAT HAS BEEN USED IS MORE THAN THE RESOURCE BUGETED FOR 10% COMPLETION OF THAT ACTIVIT.



SO I WANT TO GIVE THE RESOURCE UTILIZATION TILL THAT DATE BY MY SELF AND DONT WANT PRIMAVERA TO COMPUTE BY SIMPLY MULTIPLYING PCT COMPLETION TO TOTAL BUDGETED QUANTITY OF THAT ACTIVITY TO CALCULATE VALUES TILL THAT DATE.


P
Pranab Kumar Deb 👤 Member for 19 years 4 months

Hello Bilal,



Uncheck " Link remaining duration and schedule percent complete"



so you ca manually enter , Percent complete , remaining duration and resource used



regards



deb

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts