you can also right click on the Format Bar Chart and choose the calendar background for multiple calendars (i.e. 7 days for concrete curing and 5 day working for normal activities)
Member for
19 years
Member for19 years
Submitted by Laurie Willis on Fri, 2008-05-09 10:58
You were right, the problem was with the working pattern. There was a wrong work pattern assigned to the calendar. As soon as I set the right one, the formatting of the bars updated to what I wanted.
Thanks again!
Member for
17 years 5 months
Member for17 years6 months
Submitted by Gijs Alferink on Fri, 2008-05-09 09:36
But if you set the workpattern in your 7 days calendar there is no weekend exception so to my knowledge there wil be no weekend appearance on your barchart.
If you apply te 7 day calendar to the task.
I tried this and the 5 day calender tasks show the weekend and the 7 day calender shows no weekend.
I hope I understood you correct and have been of any help.
Member for
19 years 10 monthsRE: Formatting of bars over non-working time
Hi All
This is a problem with power project - you can only set non work folding against 1 calendar.
If I have multiple calendars I usually set the folding option to -None-.
By the way any curing time should be set on a 24hr 7day week calendar not just a 7day working week. Set the duration column to ed.
Best regards
Mike Testro
Member for
17 years 1 monthRE: Formatting of bars over non-working time
you can also right click on the Format Bar Chart and choose the calendar background for multiple calendars (i.e. 7 days for concrete curing and 5 day working for normal activities)
Member for
19 yearsRE: Formatting of bars over non-working time
Thanks fot your help Gijs.
You were right, the problem was with the working pattern. There was a wrong work pattern assigned to the calendar. As soon as I set the right one, the formatting of the bars updated to what I wanted.
Thanks again!
Member for
17 years 5 monthsRE: Formatting of bars over non-working time
Hi Laurie,
I dont know if I understoof you correct.
But if you set the workpattern in your 7 days calendar there is no weekend exception so to my knowledge there wil be no weekend appearance on your barchart.
If you apply te 7 day calendar to the task.
I tried this and the 5 day calender tasks show the weekend and the 7 day calender shows no weekend.
I hope I understood you correct and have been of any help.