REFINERY PROJECT
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
It all goes about money.
How fast can you spend it.
To Spend 17 M in 18 Months is a slow project.
I Have been on Project.
1.8 B 36 Month (Engineering had to be done in 5 countrys / Fabrication in another & Construction in another
100 M 7 Month All in One Country
360 M 12 Months All In One Country
25 M = 8 Months all in One Country.
Some times it is not possible to spend money fast enough.
So to answer it quickly if a Project Duration is 20 Month 3 to 7 % per Month
If it is 10 Month 7 to 14 % per Months
Ian Thanks.
These figures gave me a good idea.
Jorge
What sort of project? T/A involvement. No T/A Involvement
Our major project worth 17 Million US dollars with no turnaround involved took 18 months.
8 months to 10% design mainly, 11 months to 20%, then almost 10% a month to completion. Does that help?