Is PERT technique Probabilistic or deterministic?

O
Oliver Melling 👤 Member for 19 years 1 month

David,



Use the Project Management Body of Knowledge as a primary source of information for your dissertation.



The two main ones are:



APM Body of Knowledge

PMI Body of Knowledge



Each have sections on Risk Management which you can use as a reference.Try governemnt website also, you will definately find something about project risk analysis/management.

P
Philip Rawlings 👤 Member for 21 years 6 months

David

The PERT calculation takes minimum(A), most likely(B) and maximum(C) durations, calculates a working duration as (A+4B+C)/6 and doing a deterministic calculation. Then the single critical path is calculated a a rang one the end dates determined from the variances of the activities making up that single path. It is a simplistic approach dating from days when risk analyses calculation were computer-intensive and therefore expensive. It is largely unnecessary now given efficient and affordable risk analysis packages - e.g. Pertmaster www.pertmaster.com and www.primaver.com.



Hope that helps

Phil

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts