Contingency resource curves (P3e)

A
A D 👤 Member for 19 years

There are two types of contingencies for:



Known Unknowns - Risk events that u were aware of but cant be predicted. (Mostly environmental risks)



UNKNOWN UNKNOWNS - Which we never thought of



CONTINGENCY RESERVE for the Known Unknows are in-built into the activties or work packages, while MANAGEMENT RESERVES are planned for unknown unknowns.



Management reserves cannot be used by the project Manager.



Cheers,

O
Oliver Melling 👤 Member for 19 years 1 month

I agree, contingency is money you keep under the matress for when a registered risk happens.

S
Steven Oliver 👤 Member for 23 years 7 months

(IMHO) You should never plan to spend contingency, and it should therefore always be at the end of a plan.



Monies which are identified to specific Risks (as opposed to Contingency) should be allocated to the time period during which the risk is likely to occur.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts