similar to my understanding...
PEP is a document that describe how to manage the project.
It may cover construction management/method, quality control schedule(time control),contract/procurement control, EHS(saftey),document control.
to support the PEP, there will be more detail documents/precedures for each part.
to confuse
PIP= PEP + Budget
PEP is basically the method statement for the whole project in written format
Below this document (which can get revised as the project enters new phases) sits a whole raft of more detailed document - one of which is PQP. This should detail the procedures and standards which will be used on the project - anything from design safety to goods received at site to billing the client. The best procedure is of course the one on Auditing of Project Quality and Quality Performance - or doesnt anybody bother measuring Quality (or more important Quality Failure)any more in ther haste to GET THE JOB DONE ANYWAY?
Based on our experience, PQP will be part of PEP
Project Execution Plan vs Project Quality Plan?