Resources - P3 or Excel

M
manulal inasu 👤 Member for 20 years 7 months

Hi Oscar,



If your question is about graphs in excel, it is quite possible. Go to Chart options> Datalabels > and check values. you will have the values also on the bar.



Regards,



manu.

O
Oscar Wilde 👤 Member for 20 years 8 months

Is there any way when you have a long duration for your resources say 18 months to print the resources on the graph per day I know you can point and get the number but any other way



Oscar

C
Charleston-Joseph Orbe 👤 Member for 20 years 10 months

Hi Allison,



correction from my previous post



"... I can imagine ..." should be "... I can’t imagine ..."



Im sorry for the inconvenience.



Cheers



Charlie

C
Charleston-Joseph Orbe 👤 Member for 20 years 10 months

Hi Allison,



Please take note the PPeers that response to your thread comes from an environment outside IT.



Im not from IT and I can imagine the resources required in IT will be that big as that in building works, heavy civils or petrochemical/oil & gas.



I would suggest generate your resources using excel. It is simple and it is not complicated.



Regards,



Charlie

M
MARTIN EMMANUEL RAJ 👤 Member for 22 years 3 months

Allison,



Try this...



In the Resource Loading Report, In Tab Timescale - choose unit as "DAY"



your output will be in days which is your requirement.



Additionally In Tab Format - choose export to csv format. The output file created can be easily handled through Excel.



Hope this helps!!!



found any other way? pl. have your say.....



Good Luck,



Martin

S
Sukumaran Subaramaniyan 👤 Member for 21 years 3 months

Allison,



Else, go to Resource Table. Use the Resource Profile/Table dialog box to specify the requirement and filter the resources according to you preference.



Regards.

R
Raja Izat Raja Ibrahim 👤 Member for 21 years

Hi

U can use - "Tubular report > resource > loading" from there u can see distribution resource by month day hrs etc and u can roll up as per WBS or detail activities. Its will show as per schedule

S
Steven Oliver 👤 Member for 23 years 7 months

How have you loaded the resource quantity ? Hours or days ?



As far as I recall, P3 will generate a distribution based on this value.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts