Responsible for the update and coordination of Cost & Resource Loaded Transmission & Distribution Design, Construction and Commissioning programmes for Substations, Overhead Lines and Cable projects ranging from £500,000 to £30 million.
Requires constant interaction with Project Managers, Engineers, Commercial Managers and Site Teams
Create and monitor progress of detailed Design & Construction schedules
Undertake Risk Management & Scenario Planning
Undertake detailed delay analysis and claim management
Lead Planner & Scheduler, supervised a team of 16 Schedulers, 8 on Engineering and Design and 8 on construction.
My work experience contains, Planning and scheduling for Communications projects, Mining Projects, Metals refining Projects, Plower Plants, Gas Plants, Refineries, Large scale mega construction projects.
I have been involved since the setup of Project Controls within National Grid(circ 2012). I have learnt considerable amount about the challanges of introducing EVM and why it is not just the introduction of P6, peoples behaviours have a big part to play!
I have learnt that data is at the heart of making anything become reality and for that matter a key requirement in being efficient. Know your data and you are half way there.
MAYOR BLONDET BUSINESS CENTER (Chief Field Engineer)
Construction of a reinforced concrete office building with post-tensioned slab system. Participation in the elaboration of the Commitment Plan (Budget and schedule goals). Responsible for executing and controlling the progress of the work ensuring the correct execution of all productive activities according to the approved technical file, the project management plan and compliance with the specifications and technical standards accepted in the work contract.