Project Control Manager-FEED Services, Amec Foster Wheeler Thailand, Synthomer Job 5

START Date
END Date
Experience Hours (Planning & Scheduling)
1150

„       Assigned as Project Control Manager Engineering partner for polymer latex plant expansion, client Synthomer Malaysia.

„       Preparation of project control procedures, and monthly reports

„       Project setup initialization kicks start, project and document controls, procedures, calendars.

Cost Engineer - Project Control, Tullow Oil, Well Engineering Projects and Field Services

START Date
END Date
  • Earned Value Analysis
  • Budgeting
  • Cost Control
  • Variations and change management
  • Contract administration of various subcontractors
  • Monitoring and Tracking of the well costs
  • Forecasting
  • Preparation and issuing of Daily cost report to the Government as well as the Business unit
  • Data collection from the subcontractors
  • Verification of time sheets against the reported costs
  • Managing the Work Breakdown Structure for the wells by ensuring proper cost coding and reporting
  • Subcontractor engagement in relation t

Administrador y Programador de Proyectos y Actividades, INGSERV LTDA., (various projects)

START Date
END Date

Empresa : INGSERV LTDA

Ocupación : Administrador y Programador de Proyectos y

Actividades

Fecha de Inicio : Enero 27 de 2001

Fecha de Finalización : Diciembre 12 de 2001

Dirección : Carrera 44 # 29-07 Barrio El Castillo.

Teléfono : 6106296.

Planning & Project Control Engineer, Reliance Engineering Associates (P) Ltd., Jamnagar Export Refinery project

START Date
END Date

 

  • Mar 2007 to Jan 2012
      • Organization :RELIANCE PORTS & TERMINALS LIMITED, Jamnagar

     

    Worked as Planning engineer/Project Control engineer

     

    • Central Fired Heaters Group at Jamnagar

     

    • JamnagarExport Refinery Project (JERP) Clean Fuel Unit by Reliance Industries Limited

     

    Responsibilities:

    Senior Planning Manager, TECHNIP, SATORP JER PKG 2A S.A; PREEMRAFF HOP SWEDEN;BG INT LNG NIGERIA.

    START Date

    Summary

    >35 years working experience in Infrastructures (Buildings, Highways, Railroads) and Oil & Gas EPC Projects.
    Actual Position: Project Control Manager
    Education: Mechanical Engineer Graduate, Rome University, March 1974
    Languages: English: Daily use at work; Italian: Mother tongue; French/Spanish: Fair
    Computer Skills: Primavera P3/P6, MS Office

    Specialties

    Master Plans, WBS, Cost Control, Planning, Reporting, Delay Analysis, EoT Support, e

    Planning Consultant, Tehcnip, Gjoa Flowline installation - Client StatoilHydro; Rev East Flowline installation - Client Talisman Energy; YME Redevelopment Project - Client Talisman Energy

    START Date
    END Date

    The projects are referring to the installation of 5’’ – 14” subsea pipeline including installation various equipments, risers, tie-ins, umbilical, etc. Engineering, procurement, fabrication and installation of offshore pipeline on North Sea Tasks: Creating “level 4” schedules for engineering, procurement, construction and installation of subsea pipeline. Monitoring progress and making periodically reports for management and client. For an easy understanding of the project evolution I issued S-curves, histograms, and other spreadsheets for management team and client.