Site coordination

Civil / Structural Engineer, WorleyParsons, East-West Transmission Cable Tunnel Contract-EW1 Project, Tembusu Multi Utilities Complex, Proposed Davao Coal Fired Power Plant, PowerSeraya Cogeneration Power Plant 30 & 40,

START Date
END Date
Experience Hours (Planning & Scheduling)
2000
Experience Hours (Cost Management)
150
  • Managed and coordinated multidiscipline engineering activities to ensure that projects are executed in a safe, efficient, cost-effective, and timely manner
  • Acted as primary technical coordination interface with clients to ensure that their expectations are satisfied
  • Was responsible for site supervision and management of subcontractors to ensure site safety, quality and progress of the project
  • Ensured construction works carried out by the builder follow strictly to the approved structural plans
  • Reviewed and evaluated construction and shop drawings, method

Planning / Senior Planning / Project Engineer, Thyssenkrupp Ind.India Pvt.Ltd., Power Plant

START Date
END Date
Experience Hours (Planning & Scheduling)
5000
Experience Hours (Cost Management)
5000

• Project Management and in-house coordination with Workshop
• Follow up with interlinked department e.g.
Engineering/Procurement/Finance/Dispatch.
• Prepare and execute procurement plan.
• Prepare Site activities schedule and arrange equipment supplies.
• Site visits to understand criticalities and catalysing project completion
activities.
• Coordination with site & vendors
• Project Budgeting & Client invoicing activities.

Civil Engineer - Technical Engineer, Fru-Con Engineering, WASTE WATER TREATMENT PLANT

START Date
END Date
  • Appointed to introduce AutoCad (v10. & v12) to the technical office
  • Responsible for the shop-drawings team and site coordination
  • Structural & Arch. Shop drawings + piling shop drawings & coordinates
  • Technical structural solutions