Site Engineer, DELTA For Engineering And Construction, School buildings
START Date
END Date
Site Engineer
Excavation , Footings , Steel Work , Concrete Works , Block work , All Civil And Services Work
Monthly Reporte
Site Engineer
Excavation , Footings , Steel Work , Concrete Works , Block work , All Civil And Services Work
Monthly Reporte
Project Planner / Assistant Project Manager
1 Coleman Street, Structural concrete to office development on Coleman Street by Moorgate Station, London
Client: Stanhope and Bovis Lend Lease
The scheme includes major ground works, substructure concrete, and steel frame superstructure with in-situ concrete slabs.
2004 – 2005 Assistant Pr