Senior Planning Engineer - Drilling, Sakhalin Energy Investment Co Ltd, Sakhalin Energy Investment Corporation

START Date
END Date

Responsible for all Well Drilling related planning, progress and reporting activities for the offshore platforms.

A single integrated plan was set up and maintained to cover:

Detailed “People On Board”

Detailed Well Delivery Process and Drilling

Summary long term business planning for the life of the field (30+ years)

SAP CMMS Administrator, Rubicon Offshore Intl, Maintain 2 FPSO Vessel

START Date

o    SAP Helpdesk/support for end user/ Planner on Board

o   Altering and modifying, Equipment, Work Tasks, Material, Frequencies, to reflect

o   Alterations in maintenance philosophy

o    Building and improving reports on maintenance as required

o    Reviewing equipment structures from P&ID diagrams and creating a

Project Analyst (Intern), Diageo, Supply Chain and Growth

C
Chima Amadi 👤 Member for 14 years 2 months
START Date
END Date

 

RESPONSIBILITIES:

·      Analysed equipment’s fuel consumption and inventory control of Guinness engineering spares including all mechanical, electrical/ instrumentation spares such as: gas systems, compressed air and vacuum pumps, boilers and condenser, chillers, standby diesel generators,  building services; sanitation, sewage, potable water treatment plants, water distribution and electrical spares and instruments using Excel and ERP applications (MAXIMO, STRUXURE & SAP).

Section Manager - Project Controls, GMPTE, GMPTE TIF Bid

START Date
END Date

Functional Lead - Projects

Member of the SAP delivery team, implementing SAP within GMPTE, writing procedures, Transaction User Guides relating to the implementation of the SAP Project System and Investment Management modules and the interface with Primavera P6.

Section Manager – Project Controls

PLANNING ENGINEER, TFL, Streets Infrastructure - London

START Date

Planning Engineer with over 8 years experience in mining, aviation, construction and railways industries. I'm an expert in Primavera and experienced in the creation of resource and cost loaded programmes. I enjoy automating updates and reports using VBA and Primavera and I have experience with data migration and from SAP, MS Project and other databases to Primavera. I have been successful in the delivery of projects that meet client expectations, budgets and agreed specifications.

 

Assistant Project Control Manager, Essar Projects India Ltd, Refinery project, gas pipeline project, power plant project

START Date
END Date
Experience Hours (Planning & Scheduling)
2800
Experience Hours (Cost Management)
2800
Experience Hours (Forensic Analysis)
2800

Deputy Manager Project Control: Responsible for planning , scheduling and cost control function