Scheduler Engineer, SAIPEM -FRANCE, AKPO UFR Project

START Date
END Date

·         Preparation and Execution of schedules using Software “Primavera Project Planner” by updating monthly progress reports.

·         Resource/Progress Histograms,S-Curves, Bar charts, etc.

·         Preparation of Weekly and monthly Progress reports/payments.

Construction Project Planner, B&W Instrumentation and Electrical, Douglas Middelburg Optimisation Project (DMO)

START Date
END Date
      • Creating plan/program
      • Updating plan/program
      • Maintenance of plan/program
      • Keeping senior persons & client updated with status of plan/schedule
      • Planning ahead
      • Creating Matrix
      • Updating Matrix
      • Liaising with Client
      • Designing various forms for as per client’s needs
      • S-Curves and Histograms

Junior Project Planner, GTK Networking, Various Small Government Projects

START Date
END Date
      • Creating/Updating plan/program
      • Keeping Owner & client updated with status of plan/schedule
      • Look-aheads
      • Creating/Updating Matrix
      • Assisting with Procurement
      • Liaising with Client
      • Designing various forms for as per client’s needs

Application Engineer / Planner / Primavera Application / Trainer, SEPCO II, Thermal Power Project 1400 MW

START Date
END Date

 

àPlanning & Scheduling

  • Prepare L-2, L-3Network for Construction activities
  • Prepare Preliminary schedule for EPC Project
  • Prepare revised schedules.

  

àReviewing & reporting

Project Controls Lead, "Tekfen Construction and Installation Co., Inc.", PO Plant, Sadara Project

START Date
END Date

Project Controls Lead, Saudi Arabia, Feb 2013 - Sep 2013

Client: Sadara, EPC Contractor: Foster Wheeler

As the Project Controls Lead of Propylene Oxide plant of the Sadara Project, I managed the Project Controls Team in the following areas: